PRBD201802240
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 4/20/2018 (10:00 - 12:00) | 4/20/2018 | 04/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/20/2018
Patch fireproofing on structural steel as required and call for reinspection. Walls with plumbing are approved contingent on plumbing rough in approval. Remaining wall framing approved. This inspection for fifth floor only.
|
||||
Framing Inspection | Passed | 4/27/2018 (10:00 - 12:00) | 4/27/2018 | 04/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2018
Patch fire proofing on fourth floor as required and call for reinspection. Framing approval of fourth floor contingent on plumbing rough in approval.
|
||||
Framing Inspection | Passed | 5/10/2018 (10:00 - 12:00) | 5/10/2018 | 05/10/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/10/2018
Patch fireproofing as required, OK to cover when done. Fifth Floor soffit framing approved.
|
||||
Framing Inspection | Passed | 5/22/2018 (12:30 - 2:30) | 5/22/2018 | 05/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/22/2018
Fourth floor elevator lobby framing OK.
|
||||
Fire Inspection Final | Failed | 6/28/2018 (2:30 - 3:30) | 6/28/2018 | 06/28/2018 |
Building Final Inspection | Failed | 6/28/2018 (2:30 - 3:30) | 6/28/2018 | 06/28/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
06/28/2018
4th Floor: Complete installation of all doors. Complete installation of fire extinguisher cabinets. Fire caulk penetrations in two hour rated stairwell wall at north west stairwell. 5th Floor: provide apron protection under sink in unisex toilet room. Install soap dispensers. Doors not complete. Fire extinguisher cabinet not installed. Fire caulk penetrations in two hour rated stairwell wall. Final fire and electrical approvals required.
|
||||
Fire Inspection Final | Issue TCO | 6/29/2018 (8:00 - 10:00) | 6/29/2018 | 07/02/2018 |
Building Final Inspection | Issue TCO | 6/29/2018 (10:00 - 12:00) | 6/29/2018 | 07/02/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/02/2018
Corrections requested on June 29 complete. Three week temp occupancy approved to complete remaining items for final fire approval.
|
||||
Building Final Inspection | VOID | 07/13/2018 | ||
Corrections:
Miscellaneous/Other
Outstanding
06/28/2018
4th Floor: Complete installation of all doors. Complete installation of fire extinguisher cabinets. Fire caulk penetrations in two hour rated stairwell wall at north west stairwell. 5th Floor: provide apron protection under sink in unisex toilet room. Install soap dispensers. Doors not complete. Fire extinguisher cabinet not installed. Fire caulk penetrations in two hour rated stairwell wall. Final fire and electrical approvals required.
|
||||
Fire Inspection Final | Passed | 7/17/2018 (8:00 - 10:00) | 7/17/2018 | 07/17/2018 |
Building Final Inspection | Passed | 7/17/2018 (8:00 - 10:00) | 7/17/2018 | 07/17/2018 |