Permit Application Status

PRBD201802240


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201802240
Building
Finaled
MINNESOTA CENTER JV LLC
Alteration/Remodel
Business
Build out new offices, work areas, conference rooms, break rooms, and reception. Jostens, Inc.
03/20/2018
04/11/2018
01/13/2019
07/17/2018

Locations

Permits

Permit Number: PRBD201802240

Building
Finaled
04/11/2018
01/13/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 4/20/2018 (10:00 - 12:00) 4/20/2018 04/20/2018
Corrections:


Miscellaneous/Other
Comment Only
04/20/2018
Patch fireproofing on structural steel as required and call for reinspection. Walls with plumbing are approved contingent on plumbing rough in approval. Remaining wall framing approved. This inspection for fifth floor only.

Framing Inspection Passed 4/27/2018 (10:00 - 12:00) 4/27/2018 04/27/2018
Corrections:


Miscellaneous/Other
Comment Only
04/27/2018
Patch fire proofing on fourth floor as required and call for reinspection. Framing approval of fourth floor contingent on plumbing rough in approval.

Framing Inspection Passed 5/10/2018 (10:00 - 12:00) 5/10/2018 05/10/2018
Corrections:


Miscellaneous/Other
Comment Only
05/10/2018
Patch fireproofing as required, OK to cover when done. Fifth Floor soffit framing approved.

Framing Inspection Passed 5/22/2018 (12:30 - 2:30) 5/22/2018 05/22/2018
Corrections:


Miscellaneous/Other
Comment Only
05/22/2018
Fourth floor elevator lobby framing OK.

Fire Inspection Final Failed 6/28/2018 (2:30 - 3:30) 6/28/2018 06/28/2018
Building Final Inspection Failed 6/28/2018 (2:30 - 3:30) 6/28/2018 06/28/2018
Corrections:


Miscellaneous/Other
Carried Forward
06/28/2018
4th Floor: Complete installation of all doors. Complete installation of fire extinguisher cabinets. Fire caulk penetrations in two hour rated stairwell wall at north west stairwell. 5th Floor: provide apron protection under sink in unisex toilet room. Install soap dispensers. Doors not complete. Fire extinguisher cabinet not installed. Fire caulk penetrations in two hour rated stairwell wall. Final fire and electrical approvals required.

Fire Inspection Final Issue TCO 6/29/2018 (8:00 - 10:00) 6/29/2018 07/02/2018
Building Final Inspection Issue TCO 6/29/2018 (10:00 - 12:00) 6/29/2018 07/02/2018
Corrections:


Miscellaneous/Other
Comment Only
07/02/2018
Corrections requested on June 29 complete. Three week temp occupancy approved to complete remaining items for final fire approval.

Building Final Inspection VOID 07/13/2018
Corrections:


Miscellaneous/Other
Outstanding
06/28/2018
4th Floor: Complete installation of all doors. Complete installation of fire extinguisher cabinets. Fire caulk penetrations in two hour rated stairwell wall at north west stairwell. 5th Floor: provide apron protection under sink in unisex toilet room. Install soap dispensers. Doors not complete. Fire extinguisher cabinet not installed. Fire caulk penetrations in two hour rated stairwell wall. Final fire and electrical approvals required.

Fire Inspection Final Passed 7/17/2018 (8:00 - 10:00) 7/17/2018 07/17/2018
Building Final Inspection Passed 7/17/2018 (8:00 - 10:00) 7/17/2018 07/17/2018