PRBD201802292
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 6/21/2018 (8:00 - 10:00) | 6/21/2018 | 06/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2018
Phase 1 framing of the soffits in cafeteria approved.
|
||||
Footing Inspection | Passed | 7/5/2018 (10:00 - 12:00) | 7/5/2018 | 07/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/05/2018
First progress inspection of footing for new elevator pit. Rebar placement in top and bottom mats and vertical rods per plan OK.
|
||||
Framing Inspection | Passed | 8/3/2018 (8:00 - 10:00) | 8/3/2018 | 08/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/03/2018
Progress framing inspection at both Jefferson and Olson schools approved.
|
||||
Framing Inspection | Partial Pass | 8/7/2018 (8:00 - 10:00) | 8/7/2018 | 08/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/07/2018
Soffits in media room and furd out CMU wall approved downstairs bathroom north wall removed CMU wall and replaced with inch and five studs approved OK to cover
|
||||
Rough In Inspection | Partial Pass | 08/30/2018 | ||
Commercial roof - built up hot liquid . Fiberboard and Insulation. | ||||
Rough In Inspection | Passed | 08/30/2018 | ||
Roof - over new elevator addition. | ||||
Framing Inspection | Passed | 8/31/2018 (10:00 - 12:00) | 8/31/2018 | 08/31/2018 |
Building Final Inspection | Issue TCO | 8/31/2018 (10:00 - 12:00) | 8/31/2018 | 08/31/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
08/31/2018
Need final fire approval. 15 day temporary occupancy approved.
|
||||
Building Final Inspection | Passed | 11/26/2018 (8:00 - 10:00) | 11/26/2018 (AM) | 11/26/2018 |
Corrections:
Miscellaneous/Other
Resolved
11/26/2018
Need final fire approval. 15 day temporary occupancy approved.
|
||||
Fire Inspection Final | Passed | 8/31/2018 (10:00 - 12:00) | 8/31/2018 (AM) | 06/14/2019 |