PRBD201802295
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 07/11/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/11/2018
Viewed all added bar joists for the roof top unit loads. All special inspections are completed and approved for these. The details call out fastening the metal decking to the bar joists, that has not been done as yet. These added bar joists have been crossed braced to the existing bar joists which are already fastened with the metal decking. There is no issue of rotation, and the contractor will see what the engineer wants to do for fastening the decking to the new bar joists if it is actually needed.
Will verify at follow up inspection.
Approved per design.
|
||||
Framing Inspection | Partial Pass | 08/01/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/01/2018
Furred wall framing and portion framing in library approved. Ok to cover
|
||||
Miscellaneous/Other
Comment Only
08/01/2018
Cooridor D & F above ceiling approved.
|
||||
Framing Inspection | Partial Pass | 08/07/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/07/2018
2nd floor bathrooms, wall in media center, soffits in cafeteria, a this framing approved to cover.
|
||||
Framing Inspection | Partial Pass | 08/14/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/14/2018
Cafeteria soffits, hall ceiling ... approved to cover
|
||||
Framing Inspection | Passed | 08/20/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/20/2018
Soffit framing at stage area of theater... approved and can cover when sprinklers have been check by fire inspector.
|
||||
Building Final Inspection | Partial Pass | 8/22/2018 (2:30 - 3:30) | 8/22/2018 | 08/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/22/2018
Approved for temp and open to public use of the cafeteria, eagle hall, and gymnasium.
|
||||
Progress Inspection | Passed | 8/24/2018 (8:00 - 3:30) | 8/24/2018 | 08/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/24/2018
Rotunda approved for temp use and to open for public use.
2nd floor bathrooms approved for final.
|
||||
Building Final Inspection | Partial Pass | 8/30/2018 (2:30 - 3:30) | 8/30/2018 | 08/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2018
Approval for occupancy and Temp final for this permit approved. Outstanding permits associated with the remodel from the sub trades to be finaled in order to final the building permit for this scope of work.
|
||||
Fire Inspection Final | Passed | 8/30/2018 (2:30 - 3:30) | 8/30/2018 (PM) | 09/26/2018 |
Building Final Inspection | Passed | 07/01/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/01/2020
Project completed, approved to close permit
|