PRBD201803119
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 5/2/2018 (10:00 - 12:00) | 5/3/2018 | 05/03/2018 |
Corrections:
Miscellaneous/Other
Outstanding
05/03/2018
Suite 45 Framing walls - approved. A. Call for above ceiling when ready ..and remove ceiling tiles for inspection of all 2 hr firecaulk system at all penetrations at parking ramp and parking garage wall. B. Remove sprinkler head in new wall framing at ceiling, and call for city fire inspection ABOVE CEILING sprinkler inspection for removing sprinkler head in new framed wall, horn strobe in conference room, and to confirm sprinkler coverage. C. See city plan marked by inspector for wall location. D. Call for above ceiling inspection for electrical for low voltage and lighting. E. No ceiling sound insulation per Solution Builders. F. BREAK ROOM EXISTING APPEARS CODE COMPLIANT FOR ACCESSIBILITY.
Suite 50, wall framing approved. Call for above ceiling for this suite
for fire sprinkler, electrical, and low voltage.
|
||||
Fire Inspection Final | Failed | 5/11/2018 (8:00 - 10:00) | 5/11/2018 | 05/11/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
05/11/2018
Must set up fire alarm and sprinkler inspection.
|
||||
Framing Inspection | Passed | 5/11/2018 (8:00 - 10:00) | 5/11/2018 | 05/11/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/11/2018
Framing - A. Firecaulk - completed. B. Framing was approved for new walls.
|
||||
Building Final Inspection | Failed | 5/11/2018 (8:00 - 10:00) | 5/11/2018 | 05/11/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
05/11/2018
Final - need final inspections for fire sprinkler and fire alarm, electrical, and low voltage, and HVAC ?, prior to building final.
|
||||
Fire Inspection Final | Not Ready | 5/14/2018 (10:00 - 12:00) | 5/14/2018 | 05/14/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
05/14/2018
Must set up fire alarm and sprinkler inspection. Contractor must call and set up inspections.
|
||||
Building Final Inspection | Failed | 5/14/2018 (12:30 - 2:30) | 5/14/2018 | 05/14/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
05/14/2018
Final - need final inspections for fire sprinkler and fire alarm, electrical, and low voltage, and HVAC ?, prior to building final. All ceiling tile must be in place, firecaulking above ceiling approved by building inspections today.
|
||||
Fire Inspection Final | Issue TCO | 5/22/2018 (10:00 - 12:00) | 5/22/2018 | 05/22/2018 |
Corrections:
Miscellaneous/Other
Resolved
05/22/2018
Must set up fire alarm and sprinkler inspection. Contractor must call and set up inspections.
|
||||
Fire extinguisher(s) needed.
Carried Forward
05/22/2018
Fire extinguisher(s) needed. Add extinguisher in break room.
|
||||
Building Final Inspection | Passed w/ Conditions | 5/22/2018 (10:00 - 12:00) | 5/22/2018 | 05/22/2018 |
Corrections:
Miscellaneous/Other
Outstanding
05/14/2018
Final - need final inspections for fire sprinkler and fire alarm, electrical, and low voltage, and HVAC ?, prior to building final. All ceiling tile must be in place, firecaulking above ceiling approved by building inspections today.
|
||||
Miscellaneous/Other
Resolved
05/22/2018
Final - suite 45, and 50. A. Suite 45 needs a few ceiling tile installed. B. Suite 50 needs fire extinguisher installed in break room kitchen., under light switch. All other trades except fire marshal fire extinguisher have been finagled including building inspections conditional final.
|
||||
Fire Inspection Final | Passed | 5/25/2018 (8:00 - 10:00) | 5/25/2018 | 05/25/2018 |
Corrections:
Fire extinguisher(s) needed.
Resolved
05/25/2018
Fire extinguisher(s) needed. Add extinguisher in break room.
|