PRBD201803194
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Fire Rating Inspection | Pending | |||
Fire Rated Assemblies Inspection | Pending | |||
Structural Inspection | Pending | |||
Framing Inspection | Pending | |||
Progress Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
01/28/2019
Framing - A. Phase 1-2. Visual inspection of completed 2 hr fire doors. B. Need to confirm door ratings and labels already installed in existing 2 hour masonry wall with new openings. Note, no inspections requested by contractor for masonry openings, corefills, and beam sizes. C. Need to provide exiting plan and exit signage with emergency lighting. D. Assure ALL 2 hr rated roll down fire doors activate upon fire alarm. E. All 2 hr rated man swinging doors need 2 hr rated closers, and if any doors could require exiting for 50 or more people, 2 hr rated panic bar door hardware is required.
|
||||
Framing Inspection | Partial Pass | 9/6/2018 (10:00 - 12:00) | 9/6/2018 | 09/06/2018 |
Phase 1, Far East Building 1, bsmt level. A. New” Salvage” room per plan against existing 2 hr building wall. New wall framing for 2 sides of salvage room- non rated non load bearing walls, deflection track - yes. | ||||
Corrections:
Miscellaneous/Other
Outstanding
09/06/2018
Framing- Far East Building 1, per plan. Salvage room, bsmt level. A. Wall framing for non load bearing and non rated walls. 2 walls creating room against 2 hr existing building wall.
|
||||
Progress Inspection | Partial Pass | 11/26/2018 (2:30 - 3:30) | 11/26/2018 (PM) | 11/28/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
11/28/2018
Framing - A. Phase 1-2. Visual inspection of completed 2 hr fire doors. B. Need to confirm door ratings and labels already installed in existing 2 hour masonry wall with new openings. Note, no inspections requested by contractor for masonry openings, corefills, and beam sizes. C. Need to provide exiting plan and exit signage with emergency lighting. D. Assure ALL 2 hr rated roll down fire doors activate upon fire alarm. E. All 2 hr rated man swinging doors need 2 hr rated closers, and if any doors could require exiting for 50 or more people, 2 hr rated panic bar door hardware is required.
|
||||
Progress Inspection | Partial Pass | 1/28/2019 (10:00 - 12:00) | 1/28/2019 (AM) | 01/28/2019 |
Installing closers on rated fire doors. Note over 49 occupants requires panic bar hardware. Fire rated doors must latch shut with closer on door. | ||||
Corrections:
Miscellaneous/Other
Carried Forward
01/28/2019
Framing - A. Phase 1-2. Visual inspection of completed 2 hr fire doors. B. Need to confirm door ratings and labels already installed in existing 2 hour masonry wall with new openings. Note, no inspections requested by contractor for masonry openings, corefills, and beam sizes. C. Need to provide exiting plan and exit signage with emergency lighting. D. Assure ALL 2 hr rated roll down fire doors activate upon fire alarm. E. All 2 hr rated man swinging doors need 2 hr rated closers, and if any doors could require exiting for 50 or more people, 2 hr rated panic bar door hardware is required.
|