PRBD201803304
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Concrete Slab Inspection | Not Ready | 7/18/2018 (12:30 - 2:30) | 7/18/2018 | 07/18/2018 |
Concrete Slab Inspection | Passed | 7/20/2018 (8:00 - 10:00) | 7/20/2018 | 07/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/19/2018
Double mat of rebar #5@12”o.c. e.w. As per RFI #7 see photos.
Approved for concrete.
|
||||
Framing Inspection | Partial Pass | 8/10/2018 (8:00 - 10:00) | 8/10/2018 | 08/10/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/10/2018
Approved framing of walls and ramps. Ok to cover walls and sections of ramps...leave access openings for sprinkler to get piping and install sprinkler coverage if required, City to verify if needed and areas to be open for inspection.
|
||||
Framing Inspection | Passed | 8/17/2018 (8:00 - 10:00) | 8/17/2018 | 08/17/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/17/2018
Floor framing , wall and ceiling approved. Ok to cover.
Ceiling framing is being raised up at ramp locations 6”, with no change to it. Approved to raise it up and cover.
|
||||
Framing Inspection | Failed | 08/22/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/22/2018
Framing of the steel tube support system at storefront.... architect to verify the support structure being attached through the existing membrane into 20gage framing studs with the system he spec’d.
This is not consistent with plans page A9 detail 3&4.
Changes to plans to be resubmitted to City of Bloomington.
|
||||
Framing Inspection | Partial Pass | 8/27/2018 (10:00 - 12:00) | 8/27/2018 | 08/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/27/2018
The exterior box steel assembly at exterior of buildout approved to cover pending sprinkler install and inspection.
The corrections for this assembly have been done by contractor.
There is an aluminum joist system that holds the screen up, the top channel and webs have been cut out where the sprinkler piping passes through. Contractor alraedy has a fix that he will do to reconnect the sections. This will be viewed at next inspection.
|
||||
Framing Inspection | Passed | 8/31/2018 (12:30 - 2:30) | 8/31/2018 | 08/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2018
Above ceiling approved.
The aluminum webbed header system that has been cut in 4 locations is connected by 20gage framing track. If this system supports any weight other than the lightweight screen, an engineer will need to design the correct fix for this.
|
||||
Progress Inspection | Partial Pass | 9/19/2018 (10:00 - 12:00) | 9/19/2018 | 09/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/19/2018
Progress inspection.... went over handrails and guardrail requirements with contractor. Complet the work for this space, call for all trades inspections before calling for final inspection.
|
||||
Fire Inspection Final | Failed | 9/21/2018 (12:30 - 2:30) | 9/21/2018 (PM) | 09/20/2018 |
Corrections:
Miscellaneous/Other
Outstanding
09/20/2018
Advised general contractor, sub contractors and owner/operator to final fire alarm and sprinkler permits.
|
||||
Progress Inspection | Passed | 9/26/2018 (10:00 - 12:00) | 9/26/2018 | 09/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/26/2018
handrails and guards, approved.
Due to support column at back technical area exiting this in not a designated exit.
|
||||
Fire Inspection Final | Passed | 9/27/2018 (12:30 - 2:30) | 9/27/2018 (PM) | 09/27/2018 |
Building Final Inspection | Passed | 9/27/2018 (12:30 - 2:30) | 9/27/2018 | 09/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/27/2018
Final approved. Ok to open to public.
|