PRBD201803999
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
11/14/2018
Need final fire approval to include exit sign relocation. 15 day temporary occupancy approved.
|
||||
| Framing Inspection | Passed | 5/25/2018 (8:00 - 10:00) | 5/25/2018 | 05/25/2018 |
| Fire Inspection Final | Issue TCO | 11/14/2018 (8:00 - 10:00) | 11/14/2018 (AM) | 11/14/2018 |
| Building Final Inspection | Issue TCO | 11/14/2018 (8:00 - 10:00) | 11/14/2018 (AM) | 11/14/2018 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/14/2018
Need final fire approval to include exit sign relocation. 15 day temporary occupancy approved.
|
||||
| Fire Inspection Final | Passed | 11/15/2018 | ||