Permit Application Status

PRBD201804269


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201804269
Building
Finaled
FELCOR/CSS HOLDINGS SPE
Alteration/Remodel
Not Required
Demo & Remodel of Woolley's Bar in the Embassy Suites
05/09/2018
06/14/2018
05/05/2019

Locations

Permits

Permit Number: PRBD201804269

Building
Finaled
06/14/2018
05/05/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 8/10/2018 (12:30 - 2:30) 8/10/2018 08/10/2018
Corrections:


Miscellaneous/Other
Comment Only
08/10/2018
Framing of walls approved and walls only can be covered. Sprinkler inspection needed for ceilings, along with a building above ceiling inspection. 1) correct the hole left in concrete from the floor above. 4” of hard pack mineral wool and 16 gage metal plate to cover for the firestop to this hole.

Framing Inspection Partial Pass 08/10/2018
Corrections:


Miscellaneous/Other
Comment Only
08/10/2018
Office/ storage room wall framing approved to cover.

Framing Inspection Passed 8/13/2018 (12:30 - 2:30) 8/13/2018 08/13/2018
Corrections:


Miscellaneous/Other
Comment Only
08/13/2018
Fire stops corrected. Above ceiling approved and ok to cover.

Progress Inspection Partial Pass 10/11/2018
Corrections:


Miscellaneous/Other
Comment Only
10/11/2018
Progress of this buildout is ongoing and accessibility at bar is approved. 1) install occupancy load signage 2) exit signage lighting needs new batteries, change out so signage is working. 3) complete work to space.

Building Final Inspection Partial Pass 10/17/2018 (10:00 - 12:00) 10/17/2018 10/17/2018
10/15/18: Canceled inspections today for Wooley’s by Carl, general contractor, plumber isn’t ready. ajacobson 10/15/2018 1:31 PM 10/12/18: Jon Aaron let us know the building final and fire final should be cancelled for 10/12/2018 - not ready. jsmidt 10/11/2018 2:19 PM
Corrections:


Miscellaneous/Other
Comment Only
10/17/2018
1) Occupancy load to be posted 2) Possible issues for exiting , occupant load wil drive number of exits. The slider glass door is not an exit door and signage to be relocated pending the outcome. 3) set up furniture.

Fire Inspection Final Failed 10/17/2018 (10:00 - 12:00) 10/17/2018 10/17/2018
10/15/18: Canceled inspections today for Wooley’s by Carl, general contractor, plumber isn’t ready. ajacobson 10/15/2018 1:31 PM 10/12/18: Jon Aaron let us know the building final and fire final should be cancelled for 10/12/2018 - not ready. jsmidt 10/11/2018 2:19 PM
Corrections:


Miscellaneous/Other
Outstanding
10/17/2018
One painted head, fire alarm not completed, occupant load must be posted, exiting must be defined.

Building Final Inspection Partial Pass 10/19/2018 (2:30 - 3:30) 10/19/2018 10/19/2018
Corrections:


Miscellaneous/Other
Outstanding
10/19/2018
1) painted sprinkler head to be replaced located directly in front of slider door. 2) complete EH list of corrections. 3) install permanent occupancy sign, ( paper sign is not adequate for final) Approved for a temp occupancy and to open to public pending a reinspection for the final when all is corrected within 7 days.

Fire Inspection Final Partial Pass 10/19/2018 (2:30 - 3:30) 10/19/2018 10/22/2018
Corrections:


Miscellaneous/Other
Outstanding
10/17/2018
One painted head, fire alarm not completed, occupant load must be posted, exiting must be defined.

Building Final Inspection Passed 11/6/2018 (8:00 - 10:00) 11/6/2018 (AM) 11/06/2018
Corrections:


Miscellaneous/Other
Comment Only
11/06/2018
All inspections completed , final approved and ok to open to public.

Fire Inspection Final Passed 11/6/2018 (7:00 - 8:00) 11/6/2018 (AM) 11/06/2018