Summary

PRBD201804304
Building
Finaled
KKMBA BLOOMINGTON LLC
New
Not Required
New building - including landscaping and parking lot. Budget/Avis
05/10/2018
07/02/2018
05/07/2019

Locations

Permits

Permit Number: PRBD201804304

Building
Finaled
07/02/2018
05/07/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 7/11/2018 (2:30 - 3:30) 7/11/2018 07/11/2018
Corrections:


Miscellaneous/Other
Comment Only
07/11/2018
Footings as per plans. Rebar Uprights to be wet stuck as they pour. See photo for the grounding rebar for electrical ground.

Insulation Inspection Partial Pass 7/16/2018 (8:00 - 10:00) 7/16/2018 07/16/2018
Corrections:


Miscellaneous/Other
Comment Only
07/16/2018
Foundation insulation is ridgid foam at R-10. Approved.

Footing Inspection Partial Pass 7/16/2018 (8:00 - 10:00) 7/16/2018 07/16/2018
Corrections:


Miscellaneous/Other
Comment Only
07/16/2018
Foundation wall is as is masonry block with rebar at the anchor bolt locations and core filled. Approved.

Footing Inspection Passed 8/13/2018 (10:00 - 12:00) 8/13/2018 08/13/2018
Corrections:


Miscellaneous/Other
Comment Only
08/13/2018
2 pad footings , stoop slab and the ramped entry slab with 2% slope approved for concrete.

Framing Inspection Passed w/ Conditions 8/28/2018 (8:00 - 10:00) 8/28/2018 08/28/2018
Corrections:


Miscellaneous/Other
Outstanding
08/28/2018
1) install cleat at bottom plate splices . 2) install nut and washer at anchor bolt where missing. 3) fireblock walls over 10ft in height. Items can be viewed and insulation inspection, ok to proceed.

Insulation Inspection Passed 9/12/2018 (8:00 - 10:00) 9/12/2018 09/12/2018
Corrections:


Miscellaneous/Other
Comment Only
09/12/2018
Interior Insulation / poly approved. Ok to cover

Lath Inspection Passed 9/24/2018 (10:00 - 12:00) 9/24/2018 09/24/2018
Corrections:


Miscellaneous/Other
Comment Only
09/24/2018
Grade D paper, weeps, lathe and fastening... approved. Ok to brown coat

Above Ceiling Inspection Passed 10/2/2018 (10:00 - 12:00) 10/2/2018 10/02/2018
Corrections:


Miscellaneous/Other
Comment Only
10/02/2018
Ceiling framing and above ceiling approved.

Fire Inspection Final Passed w/ Conditions 10/11/2018 (10:00 - 12:00) 10/11/2018 10/11/2018
Corrections:


Address signage
Comment Only
10/11/2018
Address signage: Contractor will install numbers as discussed.

Building Final Inspection Failed 10/11/2018 (10:00 - 12:00) 10/11/2018 10/11/2018
Corrections:


Miscellaneous/Other
Comment Only
10/11/2018
Wash bay has FRP installed to cover all walls and ceiling, this was a change from the plans. The FRP now takes the place of the poly at the ceiling as a interior barrier. 1)Electrical inspection has corrections that need to be completed and final for the building final. 2) Install cash wrap. 3) complete landscape. 4) install address numbers. It is ok to transfer vehicles to this site and any other office items to site. No opening to public at this time till above items are completed and inspected for the building final.

Lighting Inspection Passed 10/12/2018
Building Final Inspection Passed 11/8/2018 (10:00 - 12:00) 11/8/2018 (AM) 11/08/2018
Please insure PRDR201808378 is closed before C/O
Corrections:


Miscellaneous/Other
Comment Only
11/08/2018
I would add protection for around gas meter.