PRBD201804926
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Failed | 7/16/2018 (10:00 - 12:00) | 7/16/2018 | 07/16/2018 |
Corrections:
Miscellaneous/Other
Outstanding
07/16/2018
Talked withcontractor about the horizontal 1 hour assembly that makes up the ceiling in the B.O.H. Passageway that is within the Walgreens buildout storage area. There is a lot of stored items that were thrown up there and damaged the integrity of the assembly.
The stored items will need to be removed and the gypsum that has popped loose and can be viewed in the passageway, needs to be refastened and re-taped. The gypsum that is viewable above the assembly from within the Walgreens space will need to be fixed / replaced where it was damaged to maintain the integrity of this assembly.
This is a condition that needs to be corrected before any final is given to this buildout. Contractor to address this issue to any parties that are involved with this buildout if this does not fall within the scope of the bid work and make sure it is corrected and inspected by city inspector prior to the building of any wall to seal up that area.
|
||||
Framing Inspection | Partial Pass | 7/30/2018 (10:00 - 12:00) | 7/30/2018 | 07/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/30/2018
Walls approved to cover.
Leave on side of utility room and walls above passageway open to view fire stops... call for inspection.
|
||||
Progress Inspection | Partial Pass | 8/1/2018 (8:00 - 10:00) | 8/1/2018 | 08/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/01/2018
Storefront framing approved, no covering till electrical and fire has done inspections.
Fire stops as noted on previous inspections are corrected.
|
||||
Progress Inspection | Partial Pass | 8/23/2018 (10:00 - 12:00) | 8/23/2018 | 08/23/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/23/2018
Firestops at storefront and at patched wall location approved and ok to cover those areas.
|
||||
Progress Inspection | Partial Pass | 8/31/2018 (10:00 - 12:00) | 8/31/2018 | 08/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2018
Firestopsat floor penetrations near store fron and in storefront, approved. Ok to close up the storefront.
|
||||
Framing Inspection | Partial Pass | 10/05/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/05/2018
Storage and sales ceiling framing approved.
|
||||
Progress Inspection | Partial Pass | 10/8/2018 (10:00 - 12:00) | 10/8/2018 | 10/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/08/2018
See inspection dated 10/5. Remaining ceiling framing to be completed and inspected, call when ready.
|
||||
Above Ceiling Inspection | Passed | 10/15/2018 (8:00 - 10:00) | 10/15/2018 | 10/15/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/15/2018
Above ceiling approved, ok to complete.
|
||||
Progress Inspection | Partial Pass | 10/30/2018 (8:00 - 10:00) | 10/30/2018 (AM) | 10/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2018
Progress ongoing.
Complete the install of furnishings, and install a rear door with smoke seal and closer. Lower bathroom mirror to 40” from floor to reflective edge. Will reinspect at final.
|
||||
Fire Inspection Final | Partial Pass | 11/1/2018 (8:00 - 10:00) | 11/1/2018 (AM) | 11/01/2018 |
Building Final Inspection | Partial Pass | 11/1/2018 (10:00 - 12:00) | 11/1/2018 (AM) | 11/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2018
Continue setup and completion of work. Approval given to stock product.
Call for final inspection when completed.
|
||||
Fire Inspection Final | Failed | 11/15/2018 (10:00 - 12:00) | 11/15/2018 (AM) | 11/15/2018 |
Corrections:
Fire doors not labeled.
Outstanding
11/15/2018
Fire doors not labeled. Corridor door has a window and appears not to be fire rated.
|
||||
Building Final Inspection | Partial Pass | 11/15/2018 (10:00 - 12:00) | 11/15/2018 (AM) | 11/15/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2018
Temp for store opening approved, not including the Birchwood beauty line area. This area is still under construction for buildout, electrical and building permit still will remain open.
1) rear door with window is not listed or labeled, contractor to provide verification of door rating or replace with a listed door.
|
||||
Miscellaneous/Other
Carried Forward
11/15/2018
See comments above as outstanding items left to close out permit.
|
||||
Fire Inspection Final | Passed | 12/5/2018 (12:30 - 2:30) | 12/5/2018 (PM) | 12/05/2018 |
Corrections:
Fire doors not labeled.
Resolved
12/05/2018
Fire doors not labeled. Corridor door has a window and appears not to be fire rated.
|
||||
Building Final Inspection | Passed | 12/5/2018 (12:30 - 2:30) | 12/5/2018 (PM) | 12/05/2018 |
Corrections:
Miscellaneous/Other
Resolved
12/05/2018
See comments above as outstanding items left to close out permit.
|
||||
Miscellaneous/Other
Comment Only
12/05/2018
Final approved, all inspections completed. Ok to remove the separation walls barrier and open the corner section of store to public. Final approved.
|
||||
Framing Inspection | Passed | 12/07/2018 |