Permit Application Status

PRBD201805806


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201805806
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Business
Interior remodel/improvement to an existing tenant space in the Mall of America. The space is 3440 sf. The work includes updating the storefront, interior floor, wall and ceiling finishes. The work also include a vibration isolation slab for the tenants planned virtual reality ride and maze components.
06/12/2018
07/11/2018
05/04/2019
11/05/2018

Locations

Permits

Permit Number: PRBD201805806

Building
Finaled
07/11/2018
05/04/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 7/27/2018 (8:00 - 10:00) 7/27/2018 07/27/2018
Corrections:


Miscellaneous/Other
Comment Only
07/27/2018
Framing at wall and theater hard lid and rear exit ..... approved to cover. Call for above ceiling inspection when ready.

Framing Inspection Partial Pass 8/6/2018 (10:00 - 12:00) 8/6/2018 08/06/2018
Corrections:


Miscellaneous/Other
Comment Only
08/06/2018
Hard lid ceilings framing and above ceiling in those areas approved. Do not cover as yet since electrical and sprinkler inspections are needed for these areas. Once the inspections are done these lids can be covered.

Progress Inspection Partial Pass 8/27/2018 (2:30 - 3:30) 8/27/2018 08/27/2018
Corrections:


Miscellaneous/Other
Comment Only
08/27/2018
Rebar mat for the seating area... this mat is designed movement of the slab and the bolting is designed to have 5” embedment which has to go through the floor and get mall approval. Will follow up with this for next inspection.

Framing Inspection Partial Pass 9/6/2018 (10:00 - 12:00) 9/6/2018 09/06/2018
Corrections:


Miscellaneous/Other
Comment Only
09/06/2018
Floor framing and firestops at through floor bolting of stage area approved. Call for inspection of ramps when ready.

Progress Inspection Passed 9/14/2018 (12:30 - 2:30) 9/14/2018 09/14/2018
Corrections:


Miscellaneous/Other
Comment Only
09/14/2018
Side ramp framing and remaining above ceiling....approved, ok to close up.

Fire Inspection Final Passed 11/2/2018 (8:00 - 10:00) 11/2/2018 (AM) 11/02/2018
Building Final Inspection Failed 11/2/2018 (8:00 - 10:00) 11/2/2018 (AM) 11/02/2018
Corrections:


Miscellaneous/Other
Comment Only
11/02/2018
1) rear exit at stairway needs a powered exit sign. 2) provide accessibility at cashwrap. Approved to continue with setup.

Building Final Inspection Passed 11/5/2018 (8:00 - 10:00) 11/5/2018 (AM) 11/05/2018
Corrections:


Miscellaneous/Other
Comment Only
11/05/2018
Cashwrap has been adapted to meet accessibility. Exit light installed. Final approved and ok to open to public.