Framing Inspection | Partial Pass | 8/23/2018 (8:00 - 10:00) | 8/23/2018 | 08/23/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/23/2018
Storefront framing approved. Ceiling framing is pending inspection for sprinkler coverage and installation, no covering till that is approved.
|
||||
Fire Inspection Final | Passed | 9/21/2018 (12:30 - 2:30) | 9/21/2018 | 09/21/2018 |
Building Final Inspection | Partial Pass | 9/21/2018 (12:30 - 2:30) | 9/21/2018 | 09/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/21/2018
The inset area to the left end checkout of the cashwrap area meets the accessibility code requirements, he display unit behind that area will need to be moved back to allow for the required access for accessibility to this checkout location.
E.H. To do inspection and give approval for use.
Temp is being given to stock store and get set up for the store opening .... opening to the public is not approved at this time.
|
||||
Building Final Inspection | Passed w/ Conditions | 9/24/2018 (12:30 - 2:30) | 9/24/2018 | 09/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2018
Final approved with a follow up inspection from EH.
See inspection from 9/21. Approved for C.O. From building inspection.
|