PRBD201806653
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Pending | |||
| Building Final Inspection | Pending | |||
| Fire Inspection Final | Pending | |||
| Insulation Inspection | Passed | 7/5/2018 (10:00 - 12:00) | 7/5/2018 | 07/05/2018 |
| Insulation Inspection | Failed | 8/6/2018 (Morning) | 8/6/2018 | 08/06/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/06/2018
Fire caulking on third floor missed a couple spots in hallway and other side of one hour firewall has to be caulked also inside rooms.
|
||||
| Insulation Inspection | Partial Pass | 08/08/2018 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/08/2018
Room 301 patch wall above door. room 305 patch hole above ceiling in closet. rooms 308,309 and 310 remove ceiling tile along the one hour rated wall to be able to see the fire caulking patch wall in utility room and fire caulk penetrations.
|
||||
|
Miscellaneous/Other
Comment Only
08/08/2018
OK to put ceiling tiles in rest of areas as long as the rest of the inspections are done electrical and fire.
|
||||
| Insulation Inspection | Passed | 8/15/2018 (10:00 - 12:00) | 8/15/2018 | 08/16/2018 |