PRBD201807218
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 9/14/2018 (12:30 - 2:30) | 9/14/2018 | 09/14/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/14/2018
First layer of gypsum board on the first side of two hour rated wall OK. Note, stage framing to be inspected separately.
|
||||
Insulation Inspection | Passed | 09/14/2018 | ||
New insulation on south wall above 12 foot height OK. | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/14/2018
New insulation on south wall above 12 foot height OK.
|
||||
Fire Rating Inspection | Passed | 9/28/2018 (8:00 - 10:00) | 9/28/2018 | 09/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2018
First layer on second side of two hour wall OK. Steel for slab at front stoop OK.
|
||||
Progress Inspection | Passed | 10/3/2018 (12:30 - 2:30) | 10/3/2018 | 10/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/03/2018
Final progress inspection of two hour rated wall approved.
|
||||
Framing Inspection | Passed | 10/12/2018 (12:30 - 2:30) | 10/12/2018 | 10/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/12/2018
Soffit framing approved.
|
||||
Framing Inspection | Passed | 10/19/2018 (8:00 - 10:00) | 10/19/2018 | 10/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/19/2018
Remaining wall framing approved.
|
||||
Framing Inspection | Passed | 11/1/2018 (12:30 - 2:30) | 11/1/2018 (PM) | 11/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2018
Platform framing and fire caulk at top of rated well OK.
|
||||
Fire Inspection Final | Not Ready | 11/14/2018 (10:00 - 12:00) | 11/14/2018 (AM) | 11/14/2018 |
Building Final Inspection | Partial Pass | 11/14/2018 (10:00 - 12:00) | 11/14/2018 (AM) | 11/14/2018 |
Corrections:
Miscellaneous/Other
Outstanding
11/14/2018
Pre-final walk-through to observe life safety issues needed to be completed to obtain temporary occupancy approval. Call for inspection of life safety issues such as completed exit signs, handrails at exterior exits and guard rails, etc.
|
||||
Fire Inspection Final | Issue TCO | 11/15/2018 (12:30 - 2:30) | 11/15/2018 (PM) | 11/15/2018 |
2 week TCO. | ||||
Building Final Inspection | Issue TCO | 11/16/2018 (12:30 - 2:30) | 11/16/2018 (PM) | 11/16/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
11/16/2018
Provide permanent career exit handrails as required. Final parking lot lighting approval required by planning department. Final fire and electrical approvals required. 15 day temp occupancy approved.
|
||||
Fire Inspection Final | Passed | 11/29/2018 (12:30 - 2:30) | 11/29/2018 (PM) | 11/29/2018 |
Building Final Inspection | Issue TCO | 11/30/2018 (10:00 - 12:00) | 11/30/2018 (AM) | 11/30/2018 |
Corrections:
Miscellaneous/Other
Resolved
11/30/2018
Provide permanent career exit handrails as required. Final parking lot lighting approval required by planning department. Final fire and electrical approvals required. 15 day temp occupancy approved.
|
||||
Miscellaneous/Other
Carried Forward
11/30/2018
Extended temporary occupancy 17 days. Still need final approval on parking lot lighting. Nursery exit handrail to be installed.
|
||||
Miscellaneous/Other
Carried Forward
12/18/2018
Extend temporary occupancy to January 1, 2019 to allow for parking lot lighting completion.
|
||||
Miscellaneous/Other
Carried Forward
12/18/2018
Extend temporary occupancy to January 1, 2019 to allow for parking lot lighting completion.
|
||||
Fire Inspection Final | VOID | 01/10/2019 | ||
Lance approved final fire for this permit, 11/29/2018. jsmidt 01/10/2019 8:17 AM | ||||
Building Final Inspection | Passed | 1/10/2019 (10:00 - 12:00) | 1/10/2019 (AM) | 01/18/2019 |
Contractor called to cancel inspection for today. Requested a call from Robert. jsmidt 01/10/2019 8:10 AM | ||||
Corrections:
Miscellaneous/Other
Resolved
01/18/2019
Extended temporary occupancy 17 days. Still need final approval on parking lot lighting. Nursery exit handrail to be installed.
|
||||
Building Final Inspection | VOID | 01/18/2019 | ||
Not required per R.Howell. jsmidt 01/18/2019 2:13 PM Extend temporary occupancy to January 1, 2019 to complete parking lot lighting. | ||||
Corrections:
Miscellaneous/Other
Outstanding
12/18/2018
Extend temporary occupancy to January 1, 2019 to allow for parking lot lighting completion.
|
||||
Miscellaneous/Other
Outstanding
12/18/2018
Extend temporary occupancy to January 1, 2019 to allow for parking lot lighting completion.
|
||||
Building Final Inspection | VOID | 01/18/2019 | ||
per R.Howell. jsmidt 01/18/2019 2:13 PM | ||||
Corrections:
Miscellaneous/Other
Outstanding
01/10/2019
Extended temporary occupancy 17 days. Still need final approval on parking lot lighting. Nursery exit handrail to be installed.
|