PRBD201807278
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Above Ceiling Inspection | Pending | |||
| Contractor cancelled due to sprinkler not being inspected yet.mshulfer 10/10/2018 11:43 AM | ||||
| Progress Inspection | Pending | |||
| Contractor cancelled due to sprinkler not being inspected yet. mshulfer 10/10/2018 11:43 AM | ||||
| Framing Inspection | Passed w/ Conditions | 8/16/2018 (8:00 - 10:00) | 8/16/2018 | 08/16/2018 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/16/2018
HVAC permit and requires above ceiling inspection. Need voice activated audibl and strobe fire alarm warning in new conference room.
|
||||
| Fire Rated Assemblies Inspection | Passed | 08/16/2018 | ||
| Firecaulk system - plumbing and electrical floor penetrations. Approved. | ||||
| Progress Inspection | Partial Pass | 9/12/2018 (Afternoon) | 9/12/2018 | 09/12/2018 |
|
Corrections:
Miscellaneous/Other
Outstanding
09/12/2018
Progress - A. Conference room-2 floor penetrations in concrete floor - 2 hr rating required. Need floor box rated information.
B. Existing electrical room - over 1500 amps and 2 panels, requires a rated door with closer and smoke gasket, and a rated 1 hour ceiling by metal studs and two layers of fire rated gypsum.
C. Cabinets with sink upon final - max counter top height 34 inch AFF.
|
||||
| Above Ceiling Inspection | Partial Pass | 9/12/2018 (Afternoon) | 9/12/2018 | 09/12/2018 |
|
Corrections:
Miscellaneous/Other
Outstanding
09/12/2018
Conference room - A. Need 2 rated floor box. B. Need one hour rated ceiling of existing electrical room, and a 45 min rated door w/closer, and smoke gasket on rated door.
|
||||
| Fire Inspection Final | Passed | 10/17/2018 (8:00 - 10:00) | 10/17/2018 | 10/17/2018 |
| Contractor cancelled due to sprinkler not being inspected yet.mshulfer 10/10/2018 11:44 AM | ||||
| Building Final Inspection | Passed | 10/17/2018 | ||
| see notes under inspector notes regarding the FSS needing to be scheduled before FINAL can be scheduled. mshulfer 10/09/2018 11:48 AM | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
10/17/2018
Final building and electrical - approved.
Fire alarm testing this week. This final is contingent upon fire alarm and strobe testing.
|
||||