PRBD201807477
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 8/15/2018 (8:00 - 10:00) | 8/15/2018 | 08/15/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/15/2018
In-fill wall and stem wall framing approved. Contractor can cover only after electrical inspection has been done and passed.
Sprinkler permit required to readjust head layout due to the removed walls.
|
||||
Building Final Inspection | Partial Pass | 9/14/2018 (12:30 - 2:30) | 9/14/2018 | 09/13/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/13/2018
Mostly cosmetic work done to this space, approved to stock furnishings into space. Finals for electrical, plumbing, and both building and fire to be completed prior to opening/ occupancy.
|
||||
Fire Inspection Final | Passed | 9/14/2018 (8:00 - 10:00) | 9/14/2018 | 09/17/2018 |
Building Final Inspection | Passed | 9/28/2018 (10:00 - 12:00) | 9/28/2018 | 09/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2018
Approved for final and opening to public.
Fire Marshall inspection not required, no other sprinkler work done for this relocation of space.
|