Summary

PRBD201807783
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Tenant remodel Fourpost restaurant remodel
07/20/2018
08/07/2018
08/03/2019
02/04/2019

Locations

Permits

Permit Number: PRBD201807783

Building
Finaled
08/07/2018
08/03/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 9/18/2018 (10:00 - 12:00) 9/18/2018 09/18/2018
Corrections:


Miscellaneous/Other
Comment Only
09/18/2018
Walls and ceiling framing of main area approved. Ok to cover. Do not cover ceiling by catwalk at water heater location, and at columns.

Above Ceiling Inspection Partial Pass 9/18/2018 (10:00 - 12:00) 9/18/2018 09/18/2018
Corrections:


Miscellaneous/Other
Comment Only
09/18/2018
Above ceiling approved and can be covered except in area of catwalk by water heater. Reinspection of that area required for the fireproofing at beam.

Progress Inspection Partial Pass 9/19/2018 (8:00 - 10:00) 9/19/2018 09/19/2018
Corrections:


Miscellaneous/Other
Comment Only
09/19/2018
Fireproofing patched, approved to cover the ceiling with the catwalk inside, and the columns. Contractor to send picture of fireproofing patch at column flange that was missed, area marked, leave open for patching and picture before covering.

Fire Inspection Final Partial Pass 10/26/2018 (12:30 - 2:30) 10/26/2018 (PM) 10/26/2018
Corrections:


Miscellaneous/Other
Comment Only
10/26/2018
Temp for stock and train.

Building Final Inspection Partial Pass 10/26/2018 (12:30 - 2:30) 10/26/2018 (PM) 10/26/2018
Corrections:


Miscellaneous/Other
Comment Only
10/26/2018
1)Install accessibility signage at fitting room. 2) change out the exit door that leads to back of house, damaged door will not hold a listing. 3) install ceiling tiles in storage. Approved to stock.

Progress Inspection Passed 10/31/2018 (8:00 - 10:00) 10/31/2018 (AM) 10/31/2018
Corrections:


Miscellaneous/Other
Comment Only
10/31/2018
Items corrected from last inspection...1) install accessibility signage to fitting room and lower the coat hook within 48” of floor. Send picture to inspector.

Building Final Inspection Passed 12/07/2018
Corrections:


Miscellaneous/Other
Comment Only
12/07/2018
Approved for final and to open to public

Fire Inspection Final Passed w/ Conditions 02/04/2019
Corrections:


Miscellaneous/Other
Comment Only
02/04/2019
Space open and finaled approved by Building Inspector in Oct. 2018