Permit Application Status

PRBD201807811


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201807811
Building
Expired
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Mercantile
Remodel of an existing retail tenant space in the mall for a new Kendra Scott Jeweler store
07/20/2018
08/14/2018
04/30/2019

Locations

Permits

Permit Number: PRBD201807811

Building
Expired
08/14/2018
04/30/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Temporary Certificate of Occupancy Inspection Pending
Framing Inspection Partial Pass 9/20/2018 (8:00 - 10:00) 9/20/2018 09/20/2018
Corrections:


Miscellaneous/Other
Comment Only
09/20/2018
Walls approved to cover. Ceiling is of light framed grid system and the metal framed soffits support off this system. Correction: 1) Metal soffits need to be supported on their own. Add supports and call for inspection. Above ceiling approved, all firestops, fire proofing, in place.

Framing Inspection Passed 9/21/2018 (10:00 - 12:00) 9/21/2018 09/21/2018
Corrections:


Miscellaneous/Other
Comment Only
09/21/2018
Ceiling framing approved, ok to cover.

Above Ceiling Inspection Passed 10/18/2018 (10:00 - 12:00) 10/18/2018 10/18/2018
Corrections:


Miscellaneous/Other
Comment Only
10/18/2018
Above ceiling and framing of suspended ceilings approved.

Temporary Certificate of Occupancy Inspection Partial Pass 10/29/2018 (8:00 - 3:30) 10/29/2018 (PM) 10/29/2018
Corrections:


Miscellaneous/Other
Comment Only
10/29/2018
Approved to stock and set up. Call for tirades and fire marshal final prion to building final. 1) correction... install smoke seal at rear door and make sure it shuts and latches.

Fire Inspection Final Passed 11/1/2018 (8:00 - 10:00) 11/1/2018 (AM) 11/01/2018
Building Final Inspection Passed 11/1/2018 (8:00 - 10:00) 11/1/2018 (AM) 11/01/2018
Corrections:


Miscellaneous/Other
Comment Only
11/01/2018
Final approved for all permit work. Ok to open to public.