PRBD201807811
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Temporary Certificate of Occupancy Inspection | Pending | |||
Framing Inspection | Partial Pass | 9/20/2018 (8:00 - 10:00) | 9/20/2018 | 09/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/20/2018
Walls approved to cover. Ceiling is of light framed grid system and the metal framed soffits support off this system. Correction: 1) Metal soffits need to be supported on their own. Add supports and call for inspection.
Above ceiling approved, all firestops, fire proofing, in place.
|
||||
Framing Inspection | Passed | 9/21/2018 (10:00 - 12:00) | 9/21/2018 | 09/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/21/2018
Ceiling framing approved, ok to cover.
|
||||
Above Ceiling Inspection | Passed | 10/18/2018 (10:00 - 12:00) | 10/18/2018 | 10/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2018
Above ceiling and framing of suspended ceilings approved.
|
||||
Temporary Certificate of Occupancy Inspection | Partial Pass | 10/29/2018 (8:00 - 3:30) | 10/29/2018 (PM) | 10/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2018
Approved to stock and set up. Call for tirades and fire marshal final prion to building final. 1) correction... install smoke seal at rear door and make sure it shuts and latches.
|
||||
Fire Inspection Final | Passed | 11/1/2018 (8:00 - 10:00) | 11/1/2018 (AM) | 11/01/2018 |
Building Final Inspection | Passed | 11/1/2018 (8:00 - 10:00) | 11/1/2018 (AM) | 11/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2018
Final approved for all permit work. Ok to open to public.
|