PRBD201807812
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Fire Inspection Final | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
10/29/2018
Final not approved. Need to provide smoke control plan/matrix and perform function test.
Fire sprinkler and smoke control zones do not match. Further evaluation needs to be performed by engineers and/or designers and zones adjusted as needed.
|
||||
Framing Inspection | Partial Pass | 9/7/2018 (8:00 - 10:00) | 9/7/2018 | 09/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/07/2018
Dimising wall, and stock room framing approved
|
||||
Framing Inspection | Partial Pass | 9/21/2018 (10:00 - 12:00) | 9/21/2018 | 09/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/20/2018
Bathroom walls and ceiling, and furred walls in sales... approved to cover.
|
||||
Framing Inspection | Passed | 10/11/2018 (Afternoon) | 10/11/2018 | 10/11/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/11/2018
Infill framing to extend ceiling clouds to wall approved.
Wall box extensions approved.
Ok to cover all pending sprinkler inspection approval.
|
||||
Fire Inspection Final | Failed | 10/25/2018 (12:30 - 2:30) | 10/25/2018 | 10/25/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
10/25/2018
Final not approved. Need to provide smoke control plan/matrix and perform function test.
|
||||
Building Final Inspection | Failed | 10/25/2018 (12:30 - 2:30) | 10/25/2018 | |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2018
No final at this time !
1) complete bathrooms with all the installed items that are to be in including mirrors and signage for accessibility.
2) temp stairs at exit to have riser heights for 7” maximum,( they can be under 7”) all within 3/8” tolerance either + or minus but not both.
3) close up spacing with at the guards to a 4” maximum space and install a smooth grippable handrail, no 2x4 handrail allowed.
4) open an access to the platform framing for inspection.
5) sprinkler zone and smoke matrix information to be sent to fire inspector.
6) smoke test to be performed for the lower level due to the zone and smoke and evac change, schedule testes at earliest convenience along with the fire, mechanical, and building inspector to be present for test.
No opening to public of this lower level till all of the above items are completed.
|
||||
Building Final Inspection | Partial Pass | 10/29/2018 (7:00 - 8:00) | 10/29/2018 (AM) | 10/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2018
Stair at exit corrected for a temp use till the metal stair is installed. Bathrooms are completed.
Approved to open to public, permitis under a temp final pending the fire and smoke control issues being corrected and the installation of the metal stairs at the lower level exit.
|
||||
Fire Inspection Final | Failed | 10/29/2018 (7:00 - 8:00) | 10/29/2018 (AM) | 10/29/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
10/29/2018
Final not approved. Need to provide smoke control plan/matrix and perform function test.
Fire sprinkler and smoke control zones do not match. Further evaluation needs to be performed by engineers and/or designers and zones adjusted as needed.
|