Permit Application Status

PRBD201807812


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201807812
Building
Expired
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
This project is a tenant improvement of an existing retail store in the Mall of America. The scope of work includes: 2-level T.I. for interior of store only; downsizing lower level, with no square foot change to upper level; erect new 1-hr fire-rated separation wall; new exit for egress compliancy; convert sales area to stock room, no storage of hazardous materials; update store finishes to current prototype; build new accessible compliant men/women restrooms; installation of new V.A.V. mechanical units, distribution via duct.
07/20/2018
08/27/2018
04/27/2019

Locations

Permits

Permit Number: PRBD201807812

Building
Expired
08/27/2018
04/27/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Fire Inspection Final Pending
Corrections:


Miscellaneous/Other
Outstanding
10/29/2018
Final not approved. Need to provide smoke control plan/matrix and perform function test. Fire sprinkler and smoke control zones do not match. Further evaluation needs to be performed by engineers and/or designers and zones adjusted as needed.

Framing Inspection Partial Pass 9/7/2018 (8:00 - 10:00) 9/7/2018 09/07/2018
Corrections:


Miscellaneous/Other
Comment Only
09/07/2018
Dimising wall, and stock room framing approved

Framing Inspection Partial Pass 9/21/2018 (10:00 - 12:00) 9/21/2018 09/20/2018
Corrections:


Miscellaneous/Other
Comment Only
09/20/2018
Bathroom walls and ceiling, and furred walls in sales... approved to cover.

Framing Inspection Passed 10/11/2018 (Afternoon) 10/11/2018 10/11/2018
Corrections:


Miscellaneous/Other
Comment Only
10/11/2018
Infill framing to extend ceiling clouds to wall approved. Wall box extensions approved. Ok to cover all pending sprinkler inspection approval.

Fire Inspection Final Failed 10/25/2018 (12:30 - 2:30) 10/25/2018 10/25/2018
Corrections:


Miscellaneous/Other
Carried Forward
10/25/2018
Final not approved. Need to provide smoke control plan/matrix and perform function test.

Building Final Inspection Failed 10/25/2018 (12:30 - 2:30) 10/25/2018
Corrections:


Miscellaneous/Other
Comment Only
10/25/2018
No final at this time ! 1) complete bathrooms with all the installed items that are to be in including mirrors and signage for accessibility. 2) temp stairs at exit to have riser heights for 7” maximum,( they can be under 7”) all within 3/8” tolerance either + or minus but not both. 3) close up spacing with at the guards to a 4” maximum space and install a smooth grippable handrail, no 2x4 handrail allowed. 4) open an access to the platform framing for inspection. 5) sprinkler zone and smoke matrix information to be sent to fire inspector. 6) smoke test to be performed for the lower level due to the zone and smoke and evac change, schedule testes at earliest convenience along with the fire, mechanical, and building inspector to be present for test. No opening to public of this lower level till all of the above items are completed.

Building Final Inspection Partial Pass 10/29/2018 (7:00 - 8:00) 10/29/2018 (AM) 10/29/2018
Corrections:


Miscellaneous/Other
Comment Only
10/29/2018
Stair at exit corrected for a temp use till the metal stair is installed. Bathrooms are completed. Approved to open to public, permitis under a temp final pending the fire and smoke control issues being corrected and the installation of the metal stairs at the lower level exit.

Fire Inspection Final Failed 10/29/2018 (7:00 - 8:00) 10/29/2018 (AM) 10/29/2018
Corrections:


Miscellaneous/Other
Carried Forward
10/29/2018
Final not approved. Need to provide smoke control plan/matrix and perform function test. Fire sprinkler and smoke control zones do not match. Further evaluation needs to be performed by engineers and/or designers and zones adjusted as needed.