PRBD201808744
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Not Ready | 9/17/2018 (8:00 - 10:00) | 9/17/2018 | 09/17/2018 |
Corrections:
Miscellaneous/Other
Outstanding
09/17/2018
Smoke partition needed for the storefront due to no hardlid being installed. Contractor to address changes with architect per this requirement.
|
||||
Miscellaneous/Other
Comment Only
09/17/2018
Framing not ready for inspection.
|
||||
Framing Inspection | Partial Pass | 10/4/2018 (8:00 - 10:00) | 10/4/2018 | 10/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/04/2018
Framing: wallls and soffits approved to cover.
|
||||
Above Ceiling Inspection | Passed | 10/30/2018 (10:00 - 12:00) | 10/30/2018 (AM) | 10/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2018
Above ceiling approved.
|
||||
Fire Inspection Final | Passed w/ Conditions | 11/15/2018 (12:30 - 2:30) | 11/15/2018 (PM) | 11/15/2018 |
Corrections:
Fire extinguisher(s) needed.
Comment Only
11/15/2018
Fire extinguisher(s) needed.
|
||||
Building Final Inspection | Partial Pass | 11/15/2018 (12:30 - 2:30) | 11/15/2018 (PM) | 11/15/2018 |
Mike Morehouse called Mel who emailed the SAC determination to Mike Morehouse. Let Jon know there's an open framing inspection due to partial pass on 10/04/2018. ajacobson/mmorehouse 11/14/2018 2:38 PM Per Mike Morehouse, no final inspection until SAC determination received and any SAC fees due must be paid. ajacobson 08/24/2018 2:52 PM | ||||
Corrections:
Miscellaneous/Other
Carried Forward
11/15/2018
1) complete plumbing and inspection.
2) electrical inspection and final needed.
3) EH has issues to be resolved, correct per Health dept requirements.
|
||||
Miscellaneous/Other
Comment Only
11/15/2018
Approved for others to come in and clean and setup space, no opening to public at this time.
|
||||
Building Final Inspection | Passed | 11/19/2018 (8:00 - 10:00) | 11/19/2018 (AM) | 11/19/2018 |
Corrections:
Miscellaneous/Other
Resolved
11/19/2018
1) complete plumbing and inspection.
2) electrical inspection and final needed.
3) EH has issues to be resolved, correct per Health dept requirements.
|
||||
Miscellaneous/Other
Comment Only
11/19/2018
Inspections completed.
Corrections with Environmental Health to be performed and business license to be applied for.
Final for this building permit is approved and pending Environmental Health approval.
|