PRBD201808969
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 9/28/2018 (12:30 - 2:30) | 9/28/2018 | 09/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2018
Wall framing approved to cover.
|
||||
Fire Inspection Final | Passed | 10/30/2018 (10:00 - 12:00) | 10/30/2018 (AM) | 10/31/2018 |
Building Final Inspection | Partial Pass | 10/31/2018 (2:30 - 3:30) | 10/31/2018 (PM) | 10/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/31/2018
1) electrical final needed.
2) complete install of cubicles.
3) install dishwasher and cover at under counter of sink piping.
Approved to continue, and to move in.. finals to be called in.
|
||||
Building Final Inspection | Passed | 12/21/2018 (10:00 - 12:00) | 12/21/2018 (AM) | 12/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2018
Final approved.
|