PRBD201809465
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 10/5/2018 (12:30 - 2:30) | 10/5/2018 | 10/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/05/2018
Framing and firestops approved for walls only of PotBelly and restrooms, except the plumbing wall of restrooms... do not cover that wall, inspections needed.
|
||||
Framing Inspection | Partial Pass | 10/25/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/25/2018
Freestanding partitions and column wrap framing approved.
|
||||
Building Final Inspection | Partial Pass | 12/7/2018 (8:00 - 10:00) | 12/7/2018 (AM) | 12/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/07/2018
approved for use of the Potbelly repand offise area. No reinspection of this area needed by building inspector.
Permit is still open for the Potbelly buildout and bathrooms.
|
||||
Building Final Inspection | Passed | 12/14/2018 (8:00 - 10:00) | 12/14/2018 (AM) | 12/14/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/14/2018
Bathroom approved to open to public.
Potbelly’s is completed and inspected by all parties... approved to open to public.
Final for this permit is approved
|
||||
Fire Inspection Final | Passed | 12/13/2018 (10:00 - 12:00) | 12/13/2018 (AM) | 12/14/2018 |