PRBD201809898
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Building Final Inspection | Pending | |||
| Framing Inspection | Partial Pass | 10/15/2018 (12:30 - 2:30) | 10/15/2018 | 10/15/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/15/2018
Walls at a north end of open area approved to cover. Contractor to leave open certain walls for sprinkler removal and relocation.
|
||||
| Framing Inspection | Passed | 10/29/2018 (8:00 - 10:00) | 10/29/2018 (AM) | 10/29/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/29/2018
Soffit framing approved.... leave open the large soffits for the sprinkler inspection.
|
||||
| Above Ceiling Inspection | Passed | 11/5/2018 (8:00 - 10:00) | 11/5/2018 (AM) | 11/05/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/05/2018
Above ceiling approved.
|
||||
| Fire Inspection Final | Partial Pass | 12/04/2018 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
12/04/2018
Ok to occupy offfice areas.
|
||||
| Fire Inspection Final | Not Ready | 12/6/2018 (8:00 - 10:00) | 12/6/2018 (AM) | 12/06/2018 |
| Building Final Inspection | Partial Pass | 12/6/2018 (8:00 - 10:00) | 12/6/2018 (AM) | 12/06/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/06/2018
Approval to occupy and use the offices, cubicle Area, and yoga and meeting rooms portions of the space only.
Permits are not signed off for the use of the kitchen area, no use of that area is to be by tenant till issues are resolved and all inspections are completed.
|
||||