Permit Application Status

PRBD201810270


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201810270
Building
Finaled
THERMO KING CORPORATION
Alteration/Remodel
Not Required
ThermoKing Remodel of existing restroom in lower level of south office area, creating ADA restrooms with shower/ locker room area.
09/05/2018
10/08/2018
07/17/2019
01/18/2019

Locations

Permits

Permit Number: PRBD201810270

Building
Finaled
10/08/2018
07/17/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 11/27/2018 (2:30 - 3:30) 11/27/2018 (PM) 11/26/2018
Corrections:


Miscellaneous/Other
Comment Only
11/26/2018
Wall framing approved pending the electrical and plumbing inspections scheduled for 11/27/18. Framing change was approved as 2ft o.c. By architect.

Above Ceiling Inspection Passed 12/27/2018 (2:30 - 3:30) 12/27/2018 (PM) 12/27/2018
Corrections:


Miscellaneous/Other
Comment Only
12/27/2018
Above ceiling approved, ok to pad out pending electrical and sprinkler approval.

Fire Inspection Final Passed 1/18/2019 (8:00 - 10:00) 1/18/2019 (AM) 01/18/2019
Building Final Inspection Passed 1/18/2019 (10:00 - 12:00) 1/18/2019 (AM) 01/18/2019
Corrections:


Miscellaneous/Other
Comment Only
01/18/2019
Final for this permit work meets code requirements and is approved.