PRBD201810652
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 9/28/2018 (8:00 - 10:00) | 9/28/2018 | 09/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2018
3rd floor sales area... furred walls, no electrical going in. The horn strobe at existing wall to be relocated, do not cover this wall.
Approved to cover all other walls only.
|
||||
Progress Inspection | Failed | 10/1/2018 (8:00 - 10:00) | 10/1/2018 | 10/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/01/2018
Discussed old existing grease hood/duct work.
Advised duct work could be abandon in place as long as it is cleaned and sealed, however, COB Mechanical has final determination.
Also advised new sandwich restaurant shall have a Type I hood/duct installed and protected with a wet chemical suppression system with water back up.
|
||||
Framing Inspection | Partial Pass | 10/3/2018 (12:30 - 2:30) | 10/3/2018 | 10/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/03/2018
Add 6 more access panels, (contractor marked locations) . Ceiling framing approved to cover and drop in panels at the drop ceiling framing.
Provide pictures of the beam locations where fire proofing is to be patched.
|
||||
Building Final Inspection | Partial Pass | 10/11/2018 (12:30 - 2:30) | 10/11/2018 | 10/11/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/11/2018
1st floor kids area approved for stock and final turnover of this area pending fire approval
|
||||
Fire Inspection Final | Partial Pass | 10/11/2018 (12:30 - 2:30) | 10/11/2018 | 10/11/2018 |
Framing Inspection | Partial Pass | 10/16/2018 (10:00 - 12:00) | 10/16/2018 | 10/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/16/2018
3rd floor “Big ticket” area approved to cover existing walls with gypsum.
|
||||
Framing Inspection | Passed | 10/25/2018 (10:00 - 12:00) | 10/25/2018 | 10/25/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2018
Freestanding partition framing approved.
|
||||
Progress Inspection | Passed | 11/5/2018 (12:30 - 2:30) | 11/5/2018 (PM) | 11/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/05/2018
Big ticket sales area above ceiling approved, pending fire sprinkler inspection.
|
||||
Fire Inspection Final | Passed | 11/9/2018 (12:30 - 2:30) | 11/9/2018 (PM) | 11/09/2018 |
Building Final Inspection | Passed | 11/9/2018 (12:30 - 2:30) | 11/9/2018 (PM) | 11/09/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/09/2018
Temp C.O. to stock with fire approval.
|