Permit Application Status

PRBD201810652


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201810652
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Mercantile
Interior alterations limited to portions of the first and third floors. Work includes demolition, new partitions, merchandise fixtures, new fitting rooms, new lighting and new finishes in areas affected.
09/11/2018
09/20/2018
05/08/2019
11/09/2018

Locations

Permits

Permit Number: PRBD201810652

Building
Finaled
09/20/2018
05/08/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 9/28/2018 (8:00 - 10:00) 9/28/2018 09/28/2018
Corrections:


Miscellaneous/Other
Comment Only
09/28/2018
3rd floor sales area... furred walls, no electrical going in. The horn strobe at existing wall to be relocated, do not cover this wall. Approved to cover all other walls only.

Progress Inspection Failed 10/1/2018 (8:00 - 10:00) 10/1/2018 10/01/2018
Corrections:


Miscellaneous/Other
Comment Only
10/01/2018
Discussed old existing grease hood/duct work. Advised duct work could be abandon in place as long as it is cleaned and sealed, however, COB Mechanical has final determination. Also advised new sandwich restaurant shall have a Type I hood/duct installed and protected with a wet chemical suppression system with water back up.

Framing Inspection Partial Pass 10/3/2018 (12:30 - 2:30) 10/3/2018 10/03/2018
Corrections:


Miscellaneous/Other
Comment Only
10/03/2018
Add 6 more access panels, (contractor marked locations) . Ceiling framing approved to cover and drop in panels at the drop ceiling framing. Provide pictures of the beam locations where fire proofing is to be patched.

Building Final Inspection Partial Pass 10/11/2018 (12:30 - 2:30) 10/11/2018 10/11/2018
Corrections:


Miscellaneous/Other
Comment Only
10/11/2018
1st floor kids area approved for stock and final turnover of this area pending fire approval

Fire Inspection Final Partial Pass 10/11/2018 (12:30 - 2:30) 10/11/2018 10/11/2018
Framing Inspection Partial Pass 10/16/2018 (10:00 - 12:00) 10/16/2018 10/16/2018
Corrections:


Miscellaneous/Other
Comment Only
10/16/2018
3rd floor “Big ticket” area approved to cover existing walls with gypsum.

Framing Inspection Passed 10/25/2018 (10:00 - 12:00) 10/25/2018 10/25/2018
Corrections:


Miscellaneous/Other
Comment Only
10/25/2018
Freestanding partition framing approved.

Progress Inspection Passed 11/5/2018 (12:30 - 2:30) 11/5/2018 (PM) 11/05/2018
Corrections:


Miscellaneous/Other
Comment Only
11/05/2018
Big ticket sales area above ceiling approved, pending fire sprinkler inspection.

Fire Inspection Final Passed 11/9/2018 (12:30 - 2:30) 11/9/2018 (PM) 11/09/2018
Building Final Inspection Passed 11/9/2018 (12:30 - 2:30) 11/9/2018 (PM) 11/09/2018
Corrections:


Miscellaneous/Other
Comment Only
11/09/2018
Temp C.O. to stock with fire approval.