PRBD201810736
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Not Ready | 10/9/2018 (10:00 - 12:00) | 10/9/2018 | 10/09/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
10/11/2018
1) plastic piping through floor to be properly firestopped.
2) holes through ceiling/ floor to be also properly sealed for a 2 hour rating.
3) All columns and large patch at beam to have the improper patching of fireproofing removed and be repatched to existing thickness coverage, follow the directions of product mixing and use for patching...Cafco Handpatch product to be used to match existing.
|
||||
Progress Inspection | Partial Pass | 10/11/2018 | ||
Corrections:
Miscellaneous/Other
Outstanding
10/11/2018
1) plastic piping through floor to be properly firestopped.
2) holes through ceiling/ floor to be also properly sealed for a 2 hour rating.
3) All columns and large patch at beam to have the improper patching of fireproofing removed and be repatched to existing thickness coverage, follow the directions of product mixing and use for patching...Cafco Handpatch product to be used to match existing.
|
||||
Miscellaneous/Other
Outstanding
10/11/2018
Floor has been bead blasted and reveals some concrete patching to maintain the 2 hour floor rating. Call for inspection once floor has been patched with concrete and prior Adex overlay.
|
||||
Progress Inspection | Partial Pass | 10/19/2018 (12:30 - 2:30) | 10/19/2018 | 10/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/19/2018
Floor areas are patched in with concrete to maintain the 2 hour rating. Approved to install the Ardex covering over floor.
|
||||
Progress Inspection | Failed | 11/2/2018 (8:00 - 10:00) | 11/2/2018 (AM) | 11/02/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/02/2018
1) fireproofing to columns and beams to be corrand installed to original depth with approved patching fireproofing. The lighter patched areas need to be stripped off due to an added taping compound added to mix that has not been tested with the mix application and cannot be done to the fireproofing mix.
2) the plastic piping through the floor above needs to be firestopped with mineral wool and intumescent fire caulked to maintain the assembly rating.
3) any holes in the floor pan above also need to be firestopped properly... mineral wool to be installed in voids with a 16 gage plate attached to pan decking and fire caulking around plate to pan decking.
4) any through floor penetrations with cast piping need to have mineral wool stuffed to fill annular space around pipe.
|
||||
Framing Inspection | Partial Pass | 11/6/2018 (Afternoon) | 11/13/2018 (PM) | 11/06/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/06/2018
Framing approved of the back rooms walls and the furred walls, and walls of storefront. Ok to cover these areas. All pending outcome of electrical inspection.
Columns and storefront lids to not be covered yet till inspected.
|
||||
Insulation Inspection | Passed | 11/13/2018 (Afternoon) | 11/13/2018 (PM) | 11/13/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2018
Fireproofing is patched and approved. Framing at columns and storefront approved. No covering storefront till inspected by electrical and fire.
Holes in the ceiling/floor filled with hard pack miner wool and covered with 16 gage metal... approved.
Plastic piping in rear of buildout to be fire stopped with mineral wool and a collar at the 4” piping.
|
||||
Framing Inspection | Passed | 11/13/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/13/2018
Framing ar columns, approved. Storefront approved, but pending electrical and fire inspection approvals prior to covering .
|
||||
Fire Inspection Final | Passed w/ Conditions | 12/13/2018 (2:30 - 3:30) | 12/13/2018 (PM) | 12/13/2018 |
Building Final Inspection | Partial Pass | 12/13/2018 (2:30 - 3:30) | 12/13/2018 (PM) | 12/13/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/13/2018
1) rear door to have smoke gasket seal installed, and closer with door to shut and latch on its own.
Complete all remaining misc work to space prior to final inspection.
Approved to stock and set up space, final inspection is required prior to occupying and opening to public.
|
||||
Building Final Inspection | Passed | 12/20/2018 (10:00 - 12:00) | 12/20/2018 (AM) | 12/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2018
Approved for final, and to open to public.
|