PRBD201811287
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 10/17/2018 (12:30 - 2:30) | 10/17/2018 | 10/17/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/17/2018
Stud framing of rated Corredor wall OK. Call for electrical rough in inspection before progress inspection of layers of gypsum board can be inspected.
|
||||
Progress Inspection | Passed | 10/18/2018 (10:00 - 12:00) | 10/18/2018 | 10/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2018
Second progress inspection rated wall approved.
|
||||
Framing Inspection | Passed | 11/13/2018 (10:00 - 12:00) | 11/13/2018 (AM) | 11/13/2018 |
Building Final Inspection | Issue TCO | 11/30/2018 (2:30 - 3:30) | 11/30/2018 (PM) | 11/30/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
11/30/2018
Add two exit signs as discussed. Need final electrical approval. 10 day temporary occupancy OK.
|
||||
Fire Inspection Final | Passed | 11/30/2018 (2:30 - 3:30) | 11/30/2018 (PM) | 12/03/2018 |
Building Final Inspection | Passed | 12/10/2018 (10:00 - 12:00) | 12/10/2018 (AM) | 12/10/2018 |
11-4: Contractor called back and rescheduled inspection so that Robert could do the final. It is rescheduled for Monday.NelsonThorpe Sarah 12/04/2018 9:35 AM | ||||
Corrections:
Miscellaneous/Other
Resolved
12/10/2018
Add two exit signs as discussed. Need final electrical approval. 10 day temporary occupancy OK.
|