Permit Application Status

PRBD201811287


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201811287
Building
Finaled
SEAGATE TECHNOLOGY INC
Alteration/Remodel
Not Required
Bring existing clean room wall up to a 1 hour rating
09/23/2018
10/12/2018
06/08/2019
12/10/2018

Locations

Permits

Permit Number: PRBD201811287

Building
Finaled
10/12/2018
06/08/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 10/17/2018 (12:30 - 2:30) 10/17/2018 10/17/2018
Corrections:


Miscellaneous/Other
Comment Only
10/17/2018
Stud framing of rated Corredor wall OK. Call for electrical rough in inspection before progress inspection of layers of gypsum board can be inspected.

Progress Inspection Passed 10/18/2018 (10:00 - 12:00) 10/18/2018 10/18/2018
Corrections:


Miscellaneous/Other
Comment Only
10/18/2018
Second progress inspection rated wall approved.

Framing Inspection Passed 11/13/2018 (10:00 - 12:00) 11/13/2018 (AM) 11/13/2018
Building Final Inspection Issue TCO 11/30/2018 (2:30 - 3:30) 11/30/2018 (PM) 11/30/2018
Corrections:


Miscellaneous/Other
Carried Forward
11/30/2018
Add two exit signs as discussed. Need final electrical approval. 10 day temporary occupancy OK.

Fire Inspection Final Passed 11/30/2018 (2:30 - 3:30) 11/30/2018 (PM) 12/03/2018
Building Final Inspection Passed 12/10/2018 (10:00 - 12:00) 12/10/2018 (AM) 12/10/2018
11-4: Contractor called back and rescheduled inspection so that Robert could do the final. It is rescheduled for Monday.NelsonThorpe Sarah 12/04/2018 9:35 AM
Corrections:


Miscellaneous/Other
Resolved
12/10/2018
Add two exit signs as discussed. Need final electrical approval. 10 day temporary occupancy OK.