PRBD201813060
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 1/7/2019 (8:00 - 10:00) | 1/7/2019 (AM) | 01/07/2019 |
Corrections:
Miscellaneous/Other
Comment Only
01/07/2019
Infloor Framing, and feeding platform approved.
|
||||
Framing Inspection | Passed | 3/4/2019 (8:00 - 10:00) | 3/4/2019 (AM) | 03/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2019
Drop ceiling hanging support approved .
|
||||
Fire Inspection Final | Passed | 3/8/2019 (8:00 - 10:00) | 3/8/2019 (PM) | 03/08/2019 |
Building Final Inspection | Passed | 3/8/2019 (8:00 - 10:00) | 3/8/2019 (AM) | 03/08/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/08/2019
Permit final and open to public approved.
|