PRBD201813500
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 12/7/2018 (12:30 - 2:30) | 12/7/2018 (PM) | 12/07/2018 |
| Above ceiling fire sprinkler - Escape fire, and above ceiling electrical still pending. Framing and tenant dividing wall firecaulking - approved | ||||
| Framing Inspection | Passed | 11/19/2018 (12:30 - 2:30) | 11/19/2018 (PM) | 12/11/2018 |
| Call for above ceiling after all trade inspections. Maintain one hour fire tenant separation wall. Firecaulk penetrations in this wall. | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
11/19/2018
Framing - approved. A. Maintain one hour existing tenant separation wall, firecaulk thru penetrations after all subcontractor work. B. Add one additional exit sign per building inspector. All exit signs to have emergency lighting. C. Call for above ceiling inspection after all trade rough in inspections, fire sprinkler, electrical, phone/low voltage, plumbing, HVAC. D. CALL FOR BUILDING INSPECTOR ABOVE CEILING INSPECTION PROIR TO CEILING TILE, AFTER ALL TRADE INSPECTIONS HAVE PASSED.
|
||||
| Progress Inspection | Passed | 12/14/2018 | ||
| Above ceiling - Need fire sprinkler inspection above ceiling prior to final fire inspection scheduled for this coming Friday. | ||||
| Above Ceiling Inspection | Passed | 12/14/2018 | ||
| Partial pass- A. still need electrical above ceiling, and fire alarm wiring. B. Need fire sprinkler above ceiling inspections. Do not pad out, until theseinspections are completed. | ||||
| Above Ceiling Inspection | Passed | 12/14/2018 | ||
| Progress Inspection | Passed | 12/14/2018 | ||
| Building Final Inspection | Passed | 12/14/2018 (12:30 - 2:30) | 12/14/2018 (PM) | 12/14/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/14/2018
Final contingent upon fire marshal final.
|
||||
| Fire Inspection Final | Passed | 12/14/2018 (12:30 - 2:30) | 12/14/2018 (PM) | 12/14/2018 |