Permit Application Status

PRBD201813522


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201813522
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Assembly, general, community halls, libraries, museums, churches
The VOID - MOA Tenant Improvement of existing retail space to include the following: New non-load bearing interior walls New storefront façade New casework and interior finishes New interior lighting New relocated exit door Area of work = 4,672sf.
10/26/2018
04/30/2019
04/08/2020
10/11/2019

Locations

Property
0102724310017

0102724310017
379 North Garden, Bloomington, MN 55425

Permits

Permit Number: PRBD201813522

Building
Finaled
02/04/2019
04/08/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Failed 2/6/2019 (10:00 - 12:00) 2/6/2019 (AM) 02/06/2019
Corrections:


Miscellaneous/Other
Comment Only
02/06/2019
Issue with rear door to back of house, (D108) . Door has been altered by added door locking hardware and does not comply with the mfg specs to rate door. Options are... 1) have mfg come out and fix door and frame to maintain rating. 2) replace door and frame with a rated assembly. Contractor to address this issue.

Progress Inspection Partial Pass 4/19/2019 (8:00 - 10:00) 4/19/2019 (AM) 04/19/2019
Corrections:


Miscellaneous/Other
Comment Only
04/19/2019
Approved to cover lid at front entry in area where they need to frame for the entry gate... this will not interfere with any electrical or sprinkler inspections.

Framing Inspection Partial Pass 4/29/2019 (10:00 - 12:00) 4/29/2019 (AM) 04/29/2019
Corrections:


Miscellaneous/Other
Comment Only
04/29/2019
Hard lid in IT Alley location approved to cover, pending electrical inspection.

Progress Inspection Partial Pass 5/2/2019 (8:00 - 10:00) 5/2/2019 (AM) 05/02/2019
Corrections:


Miscellaneous/Other
Comment Only
05/02/2019
Wall framing at front areas approved and ok to cover walls without electrical. Any walls with electrical cannot be covered until electrical inspection has been completed and approved. Approved to cover at columns. Fireproofing approved

Miscellaneous/Other
Carried Forward
05/02/2019
There is a opening in the rated ceiling where condenser line is running the through that needs to be patched. Install metal patch and 3 layers of gypsum to span opening and firestop. Will recheck at next inspection.

Framing Inspection Passed 5/8/2019 (10:00 - 12:00) 5/8/2019 (AM) 05/08/2019
Corrections:


Miscellaneous/Other
Comment Only
05/08/2019
Walls and hard lids approved to cover.

Progress Inspection Passed 6/19/2019 (8:00 - 10:00) 6/19/2019 (AM) 06/19/2019
Corrections:


Miscellaneous/Other
Resolved
06/19/2019
There is a opening in the rated ceiling where condenser line is running the through that needs to be patched. Install metal patch and 3 layers of gypsum to span opening and firestop. Will recheck at next inspection.

Miscellaneous/Other
Comment Only
06/19/2019
Framing of the raised floor platform approved.

Progress Inspection Partial Pass 7/12/2019 (8:00 - 10:00) 7/12/2019 (AM) 07/12/2019
Corrections:


Miscellaneous/Other
Comment Only
07/12/2019
Walkthrough for final. Install instruction signage at game doors for exiting. Complete front entry. Add directional exit sign to the rear exit. As per electrical inspection has requirements for 3rd party inspection... see electrical permit inspection results.

Fire Inspection Final Passed 07/16/2019
Corrections:


Miscellaneous/Other
Comment Only
07/16/2019
Fire Inspection Final approval is contingent on COB Building and Electrical Inspection Finals.

Building Final Inspection Partial Pass 7/19/2019 (8:00 - 10:00) 7/19/2019 (AM) 07/19/2019
Corrections:


Miscellaneous/Other
Comment Only
07/19/2019
Approved to bring in employees, train, and use facility. The full final is contingent on UL approval of 3rd party inspection for electrical. Install signage to inside of doors for how to exit game...( directional sticker) Install panels to portal.

Building Final Inspection Passed 7/25/2019 (10:00 - 12:00) 7/25/2019 (AM) 10/11/2019
Corrections:


Miscellaneous/Other
Comment Only
07/25/2019
Occupancy signage, directional signage to exit games, and front entry installed and completed. 3rd party electrical reports are completed and waiting inspector approval. Approved to open to public and final pending the electrical final.