PRBD201813974
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Above Ceiling Inspection | Pending | |||
| Building Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
11/13/2019
Fire final needed, HVAC final needed, electrical gave a temp and is pending the installation of the neon sign. EH to be ok for final, cleaning is needed for this space.
Not ready for final at this time.
|
||||
| Progress Inspection | Pending | 9/24/2019 (10:00 - 12:00) | ||
| Framing Inspection | Not Ready | 1/11/2019 (10:00 - 12:00) | 1/11/2019 (AM) | 01/11/2019 |
| Framing Inspection | Partial Pass | 1/17/2019 (12:30 - 2:30) | 1/17/2019 (PM) | 01/17/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/17/2019
See permit PRBD 201900567 for the prep kitchen buildout in s255.
|
||||
| Framing Inspection | Partial Pass | 2/6/2019 (8:00 - 10:00) | 2/6/2019 (AM) | 02/06/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/06/2019
Wall framing at back of house wall and the wing walls to the rear cooridor approved.
|
||||
| Framing Inspection | Failed | 8/26/2019 (2:30 - 3:30) | 8/26/2019 (PM) | 08/26/2019 |
| Permit put back into issued status per Jon Aaron.NelsonThorpe Sarah 08/23/2019 9:20 AM | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
08/26/2019
Storefront...
1) special inspection needed for all the structural steel installed by welds and bolting, to support the bulkhead and door assembly.
2) fireproofing patching needed at beam inside bulkhead and columns of storefront.
3) seal penetrations of storefront at mall bulkhead.
Reinspection needed.
|
||||
| Framing Inspection | Partial Pass | 9/4/2019 (10:00 - 12:00) | 9/4/2019 (AM) | 09/04/2019 |
|
Corrections:
Miscellaneous/Other
Resolved
09/04/2019
Storefront...
1) special inspection needed for all the structural steel installed by welds and bolting, to support the bulkhead and door assembly.
2) fireproofing patching needed at beam inside bulkhead and columns of storefront.
3) seal penetrations of storefront at mall bulkhead.
Reinspection needed.
|
||||
|
Miscellaneous/Other
Comment Only
09/04/2019
Approved to cover columns, and storefront. Leave open one side of storefront for sprinkler and electrical inspection.
|
||||
| Progress Inspection | Not Ready | 9/23/2019 (8:00 - 10:00) | 9/23/2019 (AM) | 09/24/2019 |
| Progress Inspection | Passed | 10/23/2019 (8:00 - 10:00) | 10/23/2019 (AM) | 10/23/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/23/2019
Advised on fire extinguisher locations.
|
||||
| Building Final Inspection | Failed | 11/5/2019 (8:00 - 10:00) | 11/5/2019 (AM) | 11/05/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/05/2019
Equipment is not installed, other trades are not completed. Call for all inspections once everything is installed and connected.
No final at this time.
|
||||
| Building Final Inspection | Failed | 11/6/2019 (12:30 - 2:30) | 11/6/2019 (PM) | 11/06/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2019
Progress of the buildout of this restaurant is ongoing, kitchen and bar areas are close to being completed and inspected by EH.
The general public areas have misc work being done and needs to be set up and cleaned.
|
||||
| Building Final Inspection | Partial Pass | 11/7/2019 (10:00 - 12:00) | 11/7/2019 (AM) | 11/07/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/07/2019
Approved by EH for stock and training.
Trades inspections approval for stock and training. Testing and Finals are need , no public opening or friends and family yet.
Building approval to stock and train only.
Final inspection needs all trades inspections completed and approved, and EH final.
Correction...CFM for dishwasher hood to be ramped up to capture and contain the steam that rolls out of unit.
|
||||
| Fire Inspection Final | Partial Pass | 11/7/2019 (10:00 - 12:00) | 11/7/2019 (AM) | 11/12/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/12/2019
Approved for Stock and training only.
|
||||
| Building Final Inspection | Not Ready | 11/13/2019 (2:30 - 3:30) | 11/13/2019 (PM) | 11/13/2019 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/13/2019
Fire final needed, HVAC final needed, electrical gave a temp and is pending the installation of the neon sign. EH to be ok for final, cleaning is needed for this space.
Not ready for final at this time.
|
||||
| Fire Inspection Final | Passed | 11/14/2019 (12:30 - 2:30) | 11/14/2019 (PM) | 11/14/2019 |
| Building Final Inspection | Partial Pass | 11/14/2019 (12:30 - 2:30) | 11/14/2019 (PM) | 11/14/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/14/2019
Temp occupancy approved and ok to open pending a final inspection that includes full final by Mechanical inspection and Environmental Health.
Occupancy load sign of 98 occupants to be posted by front entry.
Call in all remaining inspections for the final of this permit.
|
||||