PRBD201814937
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 1/23/2019 (2:30 - 3:30) | 1/23/2019 (PM) | 01/23/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
01/23/2019
Fire sprinklers needed at front overhead ceiling at storefront. No covering till inspection of sprinklers by fire inspector.
Contractor to add structural studs to the support wall of water heater platform, and #10 screws at attachment to wall and framing of the platform.
Firestops to be viewed from underneath with the plumbing contractor.
Framing approved pending above corrected items.
|
||||
Building Final Inspection | Passed | 02/28/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/28/2019
Final approved pending the Fire Marshal final . Approved to stock and open to public.
All firestops were checked and approved.
|
||||
Miscellaneous/Other
Comment Only
02/28/2019
All firestops were checked and approved.
|
||||
Fire Inspection Final | Passed | 02/28/2019 |