PRBD201814957
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 1/15/2019 (12:30 - 2:30) | 1/15/2019 (PM) | 01/15/2019 |
Reconfigure 1/2 of floor, other half will be vacant. A. Moving/adding a few sprinkler heads. Need fire sprinkler permit. Ceiling tile remains in place on complete floor, except for a few new walls to deck, per plan. B. Exit signage per plan required with EM lighting required upon fire Marshall final. C. No work in restrooms, elevator lobby, closets. D. Electrical being fished down walls. E. Provide above ceiling rough in for electrical and fire sprinkler. Mechanical system will not require permits. | ||||
Building Final Inspection | Passed | 3/21/2019 (8:00 - 10:00) | 3/21/2019 (AM) | 03/21/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/21/2019
Final approved.
No changes to this space layout for exiting.
|