PRBD201814957
Building
Finaled
PWA RIVERVIEW OFC TWR LP
Alteration/Repair/Replace
Not Required
Tenant Improvements
12/06/2018
12/18/2018
09/17/2019
03/21/2019

Locations

Permits

Permit Number: PRBD201814957

Building
Finaled
12/18/2018
09/17/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 1/15/2019 (12:30 - 2:30) 1/15/2019 (PM) 01/15/2019
Reconfigure 1/2 of floor, other half will be vacant. A. Moving/adding a few sprinkler heads. Need fire sprinkler permit. Ceiling tile remains in place on complete floor, except for a few new walls to deck, per plan. B. Exit signage per plan required with EM lighting required upon fire Marshall final. C. No work in restrooms, elevator lobby, closets. D. Electrical being fished down walls. E. Provide above ceiling rough in for electrical and fire sprinkler. Mechanical system will not require permits.
Building Final Inspection Passed 3/21/2019 (8:00 - 10:00) 3/21/2019 (AM) 03/21/2019
Corrections:


Miscellaneous/Other
Comment Only
03/21/2019
Final approved. No changes to this space layout for exiting.