PRBD201815079
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 08/15/2019 | ||
Insulation Inspection | Partial Pass | 08/15/2019 | ||
See corrections ongoing . | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/15/2019
Foundation below grade exterior insulation. Completed.
Exterior wall insulation by fiberglass and spray foam. Partial pass.
|
||||
Structural Inspection | Partial Pass | 08/15/2019 | ||
Structural steel inspection - columns and beams. Approved per Braun Intertec. Need final report from Braun Intertec for structural steel. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/15/2019
Structural steel - columns and beams completed. Need special inspection final report upon final.
|
||||
Framing Inspection | Partial Pass | 8/15/2019 (10:00 - 12:00) | 8/15/2019 (AM) | 08/15/2019 |
Interior framing and exterior wall framing . | ||||
Corrections:
Miscellaneous/Other
Carried Forward
08/15/2019
Structural frame - progress. A. No requirement for fire resistance frame. B. 2 story from grade has been erected with steel stud exterior wall infill framing for A STEEL I BEAM AND COLUMN PRIMARY STRUCTURE, BAR JOIST ROOF SUPPORT, AND STEEL DECKING REINFORCED POURED CONCRETE 2ND FLOOR.
|
||||
Miscellaneous/Other
Comment Only
08/15/2019
Interior framing of interior walls, and exterior walls.
|
||||
Concrete Slab Inspection | Passed | 08/15/2019 | ||
Sheathing Inspection | Passed | 08/15/2019 | ||
Exterior wall sheathing by Densglass, to exterior steel stud framing . | ||||
Housewrap Inspection | Partial Pass | 08/22/2019 | ||
Progress - 8/29/19 Progress on exterior wall and around openings. Exterior sheathing - A. SELF ADHERING building wrap. Brand = Wrap shield - SA. (SELF ADHERING). Can be installed horizontally or vertically. 36 inch wide rolls. | ||||
Progress Inspection | Partial Pass | 08/28/2019 | ||
Roof - membrane. Roof top mechanical units, structural welded bar joist supports per plan. Approved. | ||||
Housewrap Inspection | Partial Pass | 08/29/2019 | ||
Progress - exterior weather barrier over Dens glass yellow exterior sheeting. | ||||
Framing Inspection | Not Ready | 9/23/2019 (8:00 - 10:00) | 9/23/2019 (AM) | 09/23/2019 |
2nd floor - concrete. A. All floor penetrations plumbing and electrical must be fire caulked, one hour systems. B. 3 Inch or larger PVC pipe penetrations in 2nd floor require one hour rated fire stop collar installed from below. 2nd floor 1 hr rated, having standard stud shaft wall from 2nd floor to bottom of roof deck. All other framing and insulation are approved contingent upon all trade rough in inspections. | ||||
Insulation Inspection | Partial Pass | 9/23/2019 (8:00 - 10:00) | 9/23/2019 (AM) | 09/23/2019 |
Exterior walls, and roof. Approved | ||||
Progress Inspection | Partial Pass | 09/26/2019 | ||
Progress inspection. 2 hour rated floor sections, installed on the top side of the concrete second floor, to seal the concrete 2nd floor opening around all vertical 18 gage ductwork passing through 2nd floor to first floor ceiling. Note-this is creating a 2 hour fire separation system between 1st floor ceiling and 2nd floor, thus eliminating the need for a rated shaft wall. NOTE-Fire dampers are already installed in all vertical ductwork, at 2nd floor. | ||||
Progress Inspection | Passed | 10/18/2019 | ||
Progress, construct a 2 hr fire stop system by gypsum, at 2nd floor concrete slab opening, meeting the vertical mechanical ductwork penetrating the concrete floor slab. A; This is to provide a 2 hr ceiling rating for only the first floor records room designed for a 2 hr fire resistance rating. Passed. | ||||
Fire Inspection Final | Passed | 12/19/2019 (7:00 - 8:00) | 12/19/2019 (AM) | 04/13/2020 |
4/13/2020, Eric Hanson performed generator test on 4/07/2020. Passed. Partial pass of generator switchover for north side of space. | ||||
Fire Inspection Final | Passed | 04/13/2020 | ||
Pass to close permit. Final approved per Kris Kaiser. | ||||
Corrections:
Miscellaneous/Other
Comment Only
04/08/2020
Fire Inspection Final Passed pending COB Building Inspection.
|
||||
Prior to Occupancy Inspection | Passed | 12/20/2019 (10:00 - 12:00) | 12/20/2019 (AM) | 04/13/2020 |
Permission to Occupy some completed areas of new construction. | ||||
Corrections:
Miscellaneous/Other
Comment Only
12/20/2019
Prior to final, occupancy for portions of new building. A. Moving in furniture into completed offices and rooms. B. All new restrooms completed. C. Areas not completed are obvious isolated from use. D. Emergency lighting, exit signage, stairwells, and emergency generator test are completed. E. Parking lot completed. Remodel of existing ares will start in 2020. F. Fire sprinkler coverage.
G. Isolated construction office area not completed until final in 2020.
|
||||
Progress Inspection | Passed | 04/13/2020 | ||
A. Revision - One Accessible restroom with shower located on second floor. B. Progress on exterior clad/stone surfaces. Bathroom has transfer shower, but not 100% accessible. C. Must label a private bathroom approved per Duke Johnson. | ||||
Insulation Inspection | Passed | 04/13/2020 | ||
Structural Inspection | Passed | 04/13/2020 | ||
Fire Rated Assemblies Inspection | Passed | 04/13/2020 | ||
Framing Inspection | Passed | 04/13/2020 | ||
Corrections:
Miscellaneous/Other
Outstanding
08/15/2019
Structural frame - progress. A. No requirement for fire resistance frame. B. 2 story from grade has been erected with steel stud exterior wall infill framing for A STEEL I BEAM AND COLUMN PRIMARY STRUCTURE, BAR JOIST ROOF SUPPORT, AND STEEL DECKING REINFORCED POURED CONCRETE 2ND FLOOR.
|
||||
Housewrap Inspection | Passed | 04/13/2020 | ||
Framing Inspection | Passed | 04/13/2020 | ||
Progress Inspection | Passed | 04/13/2020 | ||
Prior to Occupancy Inspection | Passed | 4/13/2020 (8:00 - 10:00) | 04/13/2020 | |
Lighting Inspection Sign | Passed | 04/17/2020 | ||
Lighting inspection had previously been inspected by Londell Pease, Senior Planner. The lighting passed inspection. mcentinario 04/17/2020 3:37 PM | ||||
Landscaping Inspection | Passed | 04/17/2020 | ||
Planning staff will monitor the landscaping as spring progresses. mcentinario 04/17/2020 3:38 PM | ||||
Building Final Inspection | Passed | 04/28/2020 | ||
Project completed-special inspection reports received. | ||||
Corrections:
Miscellaneous/Other
Outstanding
04/13/2020
A. Engineering 2 conditions pending. B. Planning 2 conditions pending. (Evening exterior lighting levels) and (landscape inspections ) C. Number all exterior doors.
|
||||
Framing Inspection | Passed | 04/28/2020 | ||
Reframing configuration of new 2nd floor restroom per plan, to provide accessibility. A. Framing - 2nd floor accessible restroom with transfer shower stall, toilet, sinks. Reconfiguration for accessibility with out moving plumbing. Approved. | ||||
Corrections:
Miscellaneous/Other
Carried Forward
07/29/2019
Structural frame - progress. A. No requirement for fire resistance frame. B. 2 story from grade has been erected with steel stud exterior wall infill framing for A STEEL I BEAM AND COLUMN PRIMARY STRUCTURE, BAR JOIST ROOF SUPPORT, AND STEEL DECKING REINFORCED POURED CONCRETE 2ND FLOOR.
|
||||
Building Final Inspection | Passed | 4/13/2020 (8:00 - 10:00) | 4/13/2020 (AM) | 04/28/2020 |
See corrections | ||||
Corrections:
Miscellaneous/Other
Carried Forward
04/13/2020
A. Engineering 2 conditions pending. B. Planning 2 conditions pending. (Evening exterior lighting levels) and (landscape inspections ) C. Number all exterior doors.
|