Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 1/17/2019 (10:00 - 12:00) | 1/17/2019 (AM) | 01/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2019
Framing approved for the 2 doors and 5ft wall. No electrical in those areas. Ok to cover.those locations.
|
||||
Building Final Inspection | Passed | 2/15/2019 (8:00 - 10:00) | 2/15/2019 (AM) | 02/15/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/15/2019
Building final approved pending for Marshall final.
|
||||
Fire Inspection Final | Passed | 2/15/2019 (8:00 - 10:00) | 2/15/2019 (AM) | 02/15/2019 |