PRBD201900905
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 2/14/2019 (8:00 - 10:00) | 2/14/2019 (AM) | 02/14/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/14/2019
All exposed and visible fireproofing approved.
Went over exit doors and exiting with contractor and owner.
|
||||
Framing Inspection | Partial Pass | 2/15/2019 (12:30 - 2:30) | 2/15/2019 (PM) | 02/15/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/15/2019
Framing of rear exit door opening at rear of space approved.
Leave out ceiling panel of gypsum for fire sprinkler inspection.
|
||||
Progress Inspection | Failed | 2/19/2019 (8:00 - 10:00) | 2/19/2019 (AM) | 02/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/19/2019
Lighting and exiting gone over by fire inspector.
|
||||
Miscellaneous/Other
Carried Forward
02/22/2019
Wall panels are exposed on the back side and need to be covered with intumescent paint per building code requirements.
|
||||
Progress Inspection | Partial Pass | 2/25/2019 (10:00 - 12:00) | 2/25/2019 (AM) | 02/25/2019 |
Corrections:
Miscellaneous/Other
Resolved
02/25/2019
Wall panels are exposed on the back side and need to be covered with intumescent paint per building code requirements.
|
||||
Miscellaneous/Other
Comment Only
02/25/2019
Went over the fireproofing of wall panels, contractor has added the flame retardant additive to each gallon of paint used to recoat the panels and the foam structure at each coat of paint.
Sprinkler coverage was also gone over by fire inspector and will be following up at the next inspection.
Exit lighting and signage is in place for most of the suite and appears to be adequate for what is needed. Contractor to add exit sign over the gate entry and test EM lighting prior to inspection.
Panic hardware needed at rear exit door. Install and have completed for final inspection.
Occupancy load signage needed, (see plans for calculated load count) and to be installed near entry in visible location.
|
||||
Progress Inspection | VOID | 2/25/2019 (10:00 - 12:00) | 2/25/2019 (AM) | 02/26/2019 |
Progress Inspection | Partial Pass | 3/1/2019 (8:00 - 10:00) | 3/1/2019 (AM) | 03/01/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/01/2019
1) install panic hardware at rear door, and label suite number.
2) install smoke seal at loading door.
Occupancy signage installed at front entry, and all product rating with flame retardant paint approved.
|
||||
Building Final Inspection | Passed | 3/4/2019 (10:00 - 12:00) | 3/4/2019 (AM) | 03/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2019
Rear door hardware, smoke seal at loading doors, and labeling of suite numbers completed. All work and inspections completed .
Fire inspection to sign off wit permit and issues with marshmallow foam pit.
City has received al documentation of fire protection products used with this attraction for the materials.
Final for this permit is approved pending Fire Marshall signoff.
Approved to open to public pending Fire Marshall.
|
||||
Fire Inspection Final | Passed | 3/4/2019 (10:00 - 12:00) | 3/4/2019 (AM) | 03/15/2019 |