PRBD201901049
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 6/28/2019 (8:00 - 10:00) | 6/28/2019 (AM) | 06/28/2019 |
HOME - Exterior precast wall footing pour, and 5 interior pads, and elevator footing with 4 inch drain, per plan. Braun on site with B.Post. Vibrator on site. | ||||
Footing Inspection | Partial Pass | 7/23/2019 (8:00 - 10:00) | 7/23/2019 (AM) | 07/23/2019 |
On going footings and foundation poured concrete. Braun Intertec on site for all special inspections, concrete testing, and soil bearing testing. | ||||
Lath Inspection | Partial Pass | 1/13/2020 (10:00 - 12:00) | 1/13/2020 (AM) | 01/13/2020 |
North side stucco lathe inspection for north exterior wall section. A. System is two coat stucco, expansion joints, grade D paper, and bottom weep screed .3rd coat color finish. - passed. B. Call for south side exterior when ready. | ||||
Framing Inspection | Partial Pass | 1/27/2020 (8:00 - 10:00) | 1/27/2020 (AM) | 01/27/2020 |
Framing - walk thru progress, all levels, stairway shafts. A. Elevator shaft by masonry block, fire caulking and concrete patching inspection will be done by building inspector, by riding top of elevator cars on completion. B. Note - roof deck flutes are being plugged by ‘off white’ mineral fiber plugs. Spray dam will be final coat. C. HVAC- RATED SHAFTS WITH FLOOR LEVEL 1 AND 2 SHAFT SEPARATION BY FUSEABLE THERMAL LINK FIRE DAMPERS. | ||||
Progress Inspection | Passed | 2/10/2020 (8:00 - 10:00) | 2/10/2020 (AM) | 02/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/10/2020
Discussed requirements for sprinkler and soffit/lid for equivalency for glass enclosure around elevator.
Also discussed the need for life safety final inspection prior to allowing for stock and/or staff training.
Request knox box and keyed access on all rear (north side) stairwell exit discharge door.
General Contractor to also follow up on fire alarm/sprinkler monitoring installation and permit.
|
||||
Building Final Inspection | Partial Pass | 02/10/2020 | ||
See corrections above. | ||||
Corrections:
Miscellaneous/Other
Carried Forward
02/10/2020
Temp Final - to stock product.
A. Final fire sprinkler, with exit signage and additional EM lighting,( see comment *C. below) through out ALL all areas of the store.
B. Provide a NO PARKING sign at ( the head of all accessible parking unload spaces.) upon final only.
C. All Exit signage to have Emergency lighting, and Additional Emergency lighting throughout all spaces as required to provide a minimum of 1 foot candle of illumination through out all areas of the building, for a loss of power situation.
D. Final fire sprinkler, ( see comment C above ) exit signage, emergency lighting, required to bring in product to stock store.
E. Elevator final required for each elevator before using elevator.
F. HVAC - Seal to concrete floor deck and ductwork, with 1 hr rated system, all bottom openings of all mechanical shafts.
G. ALL SPECIAL INSPECTION summary reports e mailed to Bpost@bloomingtonmn.gov
H. All stairwells having handrails-guard rails with self closing rated doors, with smoke gaskets.
I. All open stairways must be completed prior to using.
|
||||
Fire Inspection Final | Partial Pass | 04/06/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/06/2020
Partial final approved for stock and staff only.
|
||||
Building Final Inspection | Issue CO | 07/20/2020 | ||
Corrections:
Miscellaneous/Other
Outstanding
02/10/2020
Temp Final - to stock product.
A. Final fire sprinkler, with exit signage and additional EM lighting,( see comment *C. below) through out ALL all areas of the store.
B. Provide a NO PARKING sign at ( the head of all accessible parking unload spaces.)
* C. All Exit signage to have Emergency lighting, and Additional Emergency lighting throughout all spaces as required to provide a minimum of 1 foot candle of illumination through out all areas of the building, for a loss of power situation.
D. Final fire sprinkler, ( see comment C above ) exit signage, emergency lighting, required to bring in product to stock store.
E. Elevator final required for each elevator before using elevator.
F. HVAC - Seal to concrete floor deck and ductwork, with 1 hr rated system, all bottom openings of all mechanical shafts.
G. ALL SPECIAL INSPECTION summary reports e mailed to Bpost@bloomingtonmn.gov
|