PRBD201902054
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 4/9/2019 (2:30 - 3:30) | 4/9/2019 (PM) | 04/09/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/09/2019
Floor to deck walls only approved.
At floor penetrations marked on plans onsite call for firestop inspection.
|
||||
| Framing Inspection | Partial Pass | 4/11/2019 (8:00 - 10:00) | 4/11/2019 (AM) | 04/11/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/11/2019
Verified 3 firestops through floor. Approved
|
||||
| Framing Inspection | Partial Pass | 4/16/2019 (8:00 - 10:00) | 4/16/2019 (AM) | 04/16/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/16/2019
Remaining Framing of partition walls approved.
Call for firestops at the electrical that is bing bored through floor.
|
||||
| Framing Inspection | Passed | 4/18/2019 (8:00 - 10:00) | 4/18/2019 (AM) | 04/18/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/18/2019
Al firestops in wall approved, ok to cover all walls.
Call for above ceiling inspection inspection after all non plenum rated items removed.
|
||||
| Above Ceiling Inspection | Passed | 5/9/2019 (8:00 - 10:00) | 5/9/2019 (AM) | 05/09/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/09/2019
Above ceiling approved. Contractor to remove the 2 strips of wood attached to concrete in plenum.
|
||||
| Fire Inspection Final | Passed | 6/13/2019 (8:00 - 10:00) | 6/13/2019 (AM) | 06/13/2019 |
| Building Final Inspection | Passed w/ Conditions | 6/13/2019 (8:00 - 10:00) | 6/13/2019 (AM) | 06/13/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/13/2019
Final approved pending install of smoke gaskets at stairwell doors.
Contractor will install as per this final.
|
||||