PRBD201902141
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 4/26/2019 (10:00 - 12:00) | 4/26/2019 (AM) | 04/26/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/26/2019
Wall framing approved.
|
||||
Fire Inspection Final | Passed | 06/05/2019 | ||
Per Amanda, do NOT schedule the final until the SAC has been paid. dheile 04/01/2019 3:39 PM | ||||
Corrections:
Fire extinguishers not installed.
Comment Only
06/05/2019
Fire extinguisher not installed.hang near door of break room
Final approved pending building inspection final.
|
||||
Building Final Inspection | Partial Pass | 6/6/2019 (12:30 - 2:30) | 6/6/2019 (PM) | 06/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/06/2019
1) Electrical final needed.
2) raise angled protection panel at sink to comply with accessibility height, raise panel to comply.
Approved to install cubicles and temp occupancy.
Call for all final inspections.
|
||||
Building Final Inspection | Passed w/ Conditions | 06/07/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/07/2019
Toe clearance height of the slanted protection board installed in place of trap wrap at sink is raised to comply with accessibility code requirements.
Final approved pending the Electrical final for the issued permit.
|