PRBD201902182
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 4/25/2019 (8:00 - 10:00) | 4/25/2019 (AM) | 04/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2019
Wall framing at back storage approved.
|
||||
Fire Inspection Final | Passed | 5/28/2019 (12:30 - 2:30) | 5/28/2019 (PM) | 05/28/2019 |
Building Final Inspection | Partial Pass | 5/28/2019 (12:30 - 2:30) | 5/28/2019 (PM) | 05/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/28/2019
Temp Approved for stock and training.
|
||||
Building Final Inspection | Passed | 06/07/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/07/2019
All work completed. Approved for opening and occupancy. Final approved.
|