Permit Application Status

PRBD201902496


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201902496
Building
Expired
MSP SOUTHPOINT EQUITIES LLC
Alteration/Repair/Replace
Not Required
Tenant Remodel UMB Financial ste 250
03/22/2019
04/18/2019
07/13/2020

Locations

Permits

Permit Number: PRBD201902496

Building
Expired
04/18/2019
07/13/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Framing Inspection Partial Pass 7/31/2019 (12:30 - 2:30) 7/31/2019 (PM) 07/31/2019
Framing #1. Approved. A. Framing 2 require inspection as space is building sound wall to deck between existing tenant. Framing 3 is soffits around HVAC..
Building Final Inspection Partial Pass 8/22/2019 (10:00 - 12:00) 8/22/2019 (AM) 08/22/2019
2nd floor - phase 1 of 6 ? No city stamped plans on site. A. Phase 1 - Permit Card on site, need PARTIAL PASS for above ceiling rough in, and PARTIAL PASS final (fire sprinkler/alarm , HVAC, Electrical, and Low voltage.)
Corrections:


Miscellaneous/Other
Comment Only
08/22/2019
Phase 1 final: A. Need Copy of City stamped plan on site before starting phase 2. B. Phase 1 still requires electrical final, electrical low voltage final, HVAC final, and fire sprinkler and fire alarm final. C. Building final request today- partial pass only.

Fire Inspection Final Not Ready 8/22/2019 (10:00 - 12:00) 8/22/2019 (AM) 08/29/2019
Fire Inspection Final Passed 08/29/2019
Framing Inspection Partial Pass 9/6/2019 (10:00 - 12:00) 9/6/2019 (AM) 09/06/2019
Phase 2. Framing. Partial pass. A: call for above ceiling for sprinkler, permit by Ahern fire sprinkler.
Framing Inspection Partial Pass 10/31/2019 (10:00 - 12:00) 10/31/2019 (AM) 10/31/2019
Phase 1-5. A. Phase 3, no framing. Phase 4 framing approved, partial pass,
Above Ceiling Inspection VOID 01/09/2020
Framing Inspection Passed 12/4/2019 (8:00 - 10:00) 12/4/2019 (AM) 01/15/2020
Phase 5, of 5. Framing for small huddle room.
Corrections:


Miscellaneous/Other
Comment Only
12/04/2019
Framing - phase 5 of 5. A. Framing of small huddle room. Passed.

Above Ceiling Inspection Passed 8/14/2019 (12:30 - 2:30) 8/14/2019 (PM) 01/15/2020
Phase one of 2.
Building Final Inspection Failed 1/15/2020 (8:00 - 10:00) 1/15/2020 (AM) 01/15/2020
A. Need HVAC final, and Electrical final for temp control, low voltage, office cubical partitions, and any other. B. No plumbing work as space had existing break room. C. Fire final approved 1/15/2020. D. Call for final building inspection when above items are completed...HAVING PERMIT CARD signed ON SITE !
Building Final Inspection Not Ready 1/17/2020 (8:00 - 10:00) 1/17/2020 (AM) 01/17/2020
Suite 250 - 5 phase project occupied during construction. A. Building final - A. Need electrical final, and fire final prior to building final.