Summary

PRBD201903369
Building
Finaled
PWA RIVERVIEW OFC TWR LP
Alteration/Repair/Replace
Business
Tenant Improvements Riverview office tower suite 1500
04/15/2019
04/29/2019
01/19/2020
07/23/2019

Locations

Permits

Permit Number: PRBD201903369

Building
Finaled
04/29/2019
01/19/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 5/6/2019 (12:30 - 2:30) 5/6/2019 (PM) 05/06/2019
Corrections:


Miscellaneous/Other
Comment Only
05/06/2019
Wall framing approved

Fire Inspection Final Passed w/ Conditions 07/08/2019
Corrections:


Fire extinguisher(s) needed.
Comment Only
07/08/2019
Fire extinguisher needed in break room.

Building Final Inspection Partial Pass 7/10/2019 (2:30 - 3:30) 7/10/2019 (PM) 07/10/2019
Corrections:


Miscellaneous/Other
Carried Forward
07/10/2019
Approved for temp occupancy with correction to provide front approach to sink per accessibility code requirements. Reinspection needed for this correction.

Building Final Inspection Passed 07/23/2019
Corrections:


Miscellaneous/Other
Comment Only
07/23/2019
Cabinet doors and base of cabinet were adapted to allow for a front approach to sink and meets accessibility requirements. Final approved.