PRBD201903390
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 6/18/2019 (8:00 - 10:00) | 6/18/2019 (AM) | 06/18/2019 |
Corrections:
Footing base is sized as per Approved city plans-Ok to place concrete.
Comment Only
06/18/2019
Footing base is sized as per Approved city plans-Ok to place concrete.
|
||||
Framing Inspection | Passed | 7/17/2019 (8:00 - 10:00) | 7/17/2019 (AM) | 07/17/2019 |
Front exterior and misc interior. | ||||
Framing Inspection | Partial Pass | 7/24/2019 (8:00 - 10:00) | 7/24/2019 (AM) | 07/24/2019 |
New exterior parapet metal framing, new front face framing sheeted with FRT plywood. Approved. A. Call for paper, lathe installed non continuous thru vertical control joints, and bottom weep J bead, when ready. | ||||
Framing Inspection | Partial Pass | 07/29/2019 | ||
Framing - EXTERIOR FACADE BY STUCCO. LATHE, SHEETING, FRAMING, EXPANSION JOINT, WEEP BEAD SYSTEM. PASSED | ||||
Framing Inspection | Passed w/ Conditions | 9/9/2019 (8:00 - 10:00) | 9/9/2019 (AM) | 09/09/2019 |
Inspector notes for inspections were on the building permit. | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/09/2019
Sign permit required. Must follow city approved plan.
|
||||
Fire Inspection Final | Passed | 09/27/2019 | ||
Building Final Inspection | Passed | 10/31/2019 (8:00 - 10:00) | 10/31/2019 (AM) | 11/01/2019 |