PRBD201903491
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 11/4/2019 (8:00 - 10:00) | 11/4/2019 (AM) | 11/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/04/2019
Progress inspection of strip footings in south west area of building approved.
|
||||
Progress Inspection | Passed | 11/19/2019 (10:00 - 12:00) | 11/19/2019 (AM) | 11/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/19/2019
Progress inspection of foundation wall along column line 6, approved.
|
||||
Progress Inspection | Passed | 11/25/2019 (10:00 - 12:00) | 11/25/2019 (AM) | 11/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/25/2019
Portion of foundation wall at east end of building 2 approved.
|
||||
Progress Inspection | Passed | 12/4/2019 (8:00 - 10:00) | 12/4/2019 (AM) | 12/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/05/2019
Strip footings and pad footings as per plan marked in field approved.
|
||||
Progress Inspection | Passed | 12/16/2019 (8:00 - 10:00) | 12/16/2019 (AM) | 12/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/16/2019
Progress inspection of the foundation wall at north west corner approved.
|
||||
Miscellaneous/Other
Comment Only
12/17/2019
10 folding pads and strip footing at south east wall as per plan, approved.
|
||||
Progress Inspection | Passed | 12/23/2019 | 12/23/2019 (AM) | 12/23/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/23/2019
Pad footing around sump area approved.
|
||||
Progress Inspection | Passed | 1/6/2020 (8:00 - 10:00) | 1/6/2020 (AM) | 01/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/07/2020
Strip footings, two pad footings, and elevator pad footing as per plan approved.
|
||||
Progress Inspection | Passed | 1/23/2020 (8:00 - 10:00) | 1/23/2020 (AM) | 01/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/23/2020
Pad footings, strip footings and poured walls as per field marked plan OK. Note, clean rebar before pouring footings.
|
||||
Progress Inspection | Not Ready | 1/29/2020 (8:00 - 10:00) | 1/29/2020 (AM) | 01/29/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/29/2020
No inspection needed today.
|
||||
Progress Inspection | Passed | 2/5/2020 (8:00 - 10:00) | 2/5/2020 (AM) | 02/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/04/2020
Foundation wall inspection along north wall toward East end approved.
|
||||
Progress Inspection | Passed | 2/11/2020 (8:00 - 10:00) | 2/11/2020 (AM) | 02/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/11/2020
Poured wall and progress on elevator wall approved.
|
||||
Progress Inspection | Passed | 2/24/2020 (8:00 - 10:00) | 2/24/2020 (AM) | 02/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/24/2020
Poured wall on southside from column lines 22 through 29 approved.
|
||||
Progress Inspection | Passed | 2/28/2020 (8:00 - 10:00) | 2/28/2020 (AM) | 02/28/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/28/2020
Footings for porch area off north side approved.
|
||||
Progress Inspection | Passed | 3/6/2020 (8:00 - 10:00) | 3/4/2020 (AM) | 03/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2020
Foundation wall at North side entrance. Approved.
|
||||
Progress Inspection | Passed | 3/20/2020 (8:00 - 10:00) | 3/20/2020 (AM) | 03/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/20/2020
Rebar for slab at north entry approved.
|
||||
Progress Inspection | Passed | 3/30/2020 (8:00 - 10:00) | 3/30/2020 (AM) | 03/31/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/31/2020
Progress inspection of structural steel framing on first floor approved.
|
||||
Progress Inspection | Passed | 4/1/2020 (8:00 - 10:00) | 4/1/2020 (AM) | 04/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/01/2020
Reviewed city approved structural plans for steel framing at healthcare center building.
|
||||
Progress Inspection | Passed w/ Conditions | 4/7/2020 (8:00 - 10:00) | 4/7/2020 (AM) | 04/07/2020 |
Corrections:
Miscellaneous/Other
Outstanding
04/07/2020
Progress inspection on chimney reveals most recent pour lacked proper vibrating. Confirm with special inspector that recent pour is acceptable.
|
||||
Progress Inspection | Passed | 4/21/2020 (8:00 - 10:00) | 4/21/2020 (AM) | 04/21/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/21/2020
Progress inspection of various items approved.
|
||||
Progress Inspection | Passed | 4/29/2020 (8:00 - 10:00) | 4/29/2020 (AM) | 04/29/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/29/2020
Progress inspection of second-floor steel framing. No issues.
|
||||
Progress Inspection | Passed w/ Conditions | 4/30/2020 (8:00 - 10:00) | 4/30/2020 (AM) | 04/30/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/30/2020
Reviewed noise concerns and hours of operation with superintendent on site. He is addressing all issues.
|
||||
Progress Inspection | Passed | 5/6/2020 (8:00 - 10:00) | 5/6/2020 (AM) | 05/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2020
Progress inspection to review details on rated wall intersections.
|
||||
Progress Inspection | Passed | 5/5/2020 (8:00 - 10:00) | 5/5/2020 (AM) | 05/12/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/12/2020
Informational inspection only, reviewed plans and questions with contractor and field personnel.
|
||||
Progress Inspection | Passed | 6/3/2020 (12:30 - 2:30) | 6/3/2020 (PM) | 06/03/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/03/2020
Reviewed progress on miscellaneous framing and structural steel fire proofing. Reviewed comments with superintendent on site.
|
||||
Progress Inspection | Passed | 6/17/2020 (10:00 - 12:00) | 6/17/2020 (AM) | 06/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/17/2020
Met with drywall contractor in field to review proposed changes in methods to provide adequate rated wall and ceiling protections. Meeting to follow.
|
||||
Progress Inspection | Passed | 6/24/2020 (10:00 - 12:00) | 6/24/2020 (AM) | 06/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/24/2020
Progress inspection to review details of two hour separation walls at corridors.
|
||||
Progress Inspection | Passed | 7/7/2020 (12:30 - 2:30) | 7/7/2020 (PM) | 07/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/07/2020
Two front footings for canopy approved.
|
||||
Progress Inspection | Passed | 7/10/2020 (8:00 - 10:00) | 7/10/2020 (AM) | 07/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/10/2020
Progress inspection on framing and retaining wall at Westside OK.
|
||||
Progress Inspection | Passed | 7/24/2020 (8:00 - 10:00) | 7/24/2020 (AM) | 07/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/24/2020
Progress inspection on fire rated walls along corridors on all levels. Inspection of fire proofing on structural steel over lobby area. All approved.
|
||||
Progress Inspection | Passed | 7/31/2020 (8:00 - 10:00) | 7/31/2020 (AM) | 07/31/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/31/2020
Progress inspection of brick and stone veneers, OK. Progress on fire proofing of structural steel approved.
|
||||
Progress Inspection | Passed | 8/7/2020 (8:00 - 10:00) | 8/7/2020 (AM) | 08/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/07/2020
Progress inspection of roof approved. Progress inspection of rated walls above ceiling with fire caulk panels in place approved. Progress inspection of housewrap and flashings approved.
|
||||
Progress Inspection | Passed | 8/14/2020 (8:00 - 10:00) | 8/14/2020 (AM) | 08/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/13/2020
Progress inspection included fire caulking, meeting with fire caulking special inspector, progress on roof, exterior rework of foundation damproofing.
|
||||
Progress Inspection | Passed | 8/18/2020 (8:00 - 10:00) | 8/18/2020 (AM) | 08/18/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/18/2020
Fire caulking improvements made on south wing of building approved.
|
||||
Progress Inspection | Passed | 8/24/2020 (8:00 - 10:00) | 8/24/2020 (AM) | 08/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/24/2020
Fire caulking in third-floor corridor approved.
|
||||
Progress Inspection | Passed | 9/1/2020 (8:00 - 10:00) | 9/1/2020 (AM) | 09/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/01/2020
Progress inspection in attic of entry atrium approved. Reviewed scheduling issues and confirmed new schedule needs with contractor.
|
||||
Progress Inspection | Failed | 9/18/2020 (8:00 - 10:00) | 9/18/2020 (AM) | 09/18/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
09/24/2020
Insulation in exterior walls on third floor need correction to ensure complete filling of cavities between studs. Call for reinspection.
|
||||
Progress Inspection | Passed | 9/22/2020 (8:00 - 10:00) | 9/22/2020 (AM) | 09/23/2020 |
Corrections:
Miscellaneous/Other
Resolved
09/23/2020
Progress inspection of insulation and vapor barrier‘s on third floor reveal gaps in insulation needing correction. Drywaller‘s are not to begin work until confirmed that vapor barrier has been approved. Follow up inspections are required.
|
||||
Miscellaneous/Other
Comment Only
09/23/2020
Corrections completed on insulation issues on third floor. Progress inspection of additional insulation on third floor approved.
|
||||
Progress Inspection | Passed | 9/29/2020 (8:00 - 10:00) | 9/29/2020 (AM) | 09/29/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/29/2020
Progress inspection of exterior wall insulation at third floor atrium and progress on above ceiling fire caulking at first floor Corredor‘s.
|
||||
Progress Inspection | Passed | 10/2/2020 (8:00 - 10:00) | 10/2/2020 (AM) | 10/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/02/2020
Insulation inspection in miscellaneous rooms on second floor approved as marked in field. Call for vapor barrier inspection when ready.
|
||||
Progress Inspection | Passed | 10/6/2020 (8:00 - 10:00) | 10/6/2020 (AM) | 10/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/06/2020
Progress inspection of vapor barriers on second floor approved.
|
||||
Progress Inspection | Passed | 10/7/2020 (8:00 - 10:00) | 10/7/2020 (AM) | 10/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/07/2020
Progress inspection of remaining rooms insulated on second floor approved. Reviewed progress of two hour rated trash chute and discussed corrections required in the field.
|
||||
Progress Inspection | Passed | 10/9/2020 (8:00 - 10:00) | 10/9/2020 (AM) | 10/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/09/2020
Remaining vapor barrier inspections in second floor units approved. Reviewed rated trash chute wall corrections required.
|
||||
Progress Inspection | Passed | 10/13/2020 (8:00 - 10:00) | 10/13/2020 (AM) | 10/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/13/2020
Framing of garage level kitchen approved. Call for inspection of fire caulking of penetrations in poured wall separating kitchen from garage.
|
||||
Progress Inspection | Partial Pass | 10/19/2020 (8:00 - 10:00) | 10/19/2020 (AM) | 10/19/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
10/28/2020
Fill in gaps in insulation in room 132. Need to confirm method of insulation for projections over windows in East wing rooms number 118, 119, 124, 125, 149 and 152.
|
||||
Progress Inspection | Passed | 10/21/2020 (8:00 - 10:00) | 10/21/2020 (AM) | 10/21/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/21/2020
Exterior insulation and vapor barrier in first floor units approved. Some corrections required and noted in field, OK to proceed when completed.
|
||||
Progress Inspection | Passed | 10/22/2020 (8:00 - 10:00) | 10/22/2020 (AM) | 10/22/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/22/2020
Additional insulation and vapor barrier’s approved in first floor rooms
|
||||
Progress Inspection | Passed | 10/23/2020 (8:00 - 10:00) | 10/23/2020 (AM) | 10/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/23/2020
Progress inspection of vapor barrier’s on exterior walls of first floor rooms approved.
|
||||
Progress Inspection | Passed | 10/27/2020 (8:00 - 10:00) | 10/27/2020 (AM) | 10/27/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/27/2020
Insulation and vapor barrier’s inspected on first floor approved.
|
||||
Progress Inspection | Passed | 10/29/2020 (10:00 - 12:00) | 10/29/2020 (AM) | 10/29/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2020
Progress inspection on rated shaft approved. Some corrections required and reviewed infield to be inspected on follow up inspections.
|
||||
Progress Inspection | Passed | 11/10/2020 (8:00 - 10:00) | 11/10/2020 (AM) | 11/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/10/2020
Progress inspection of rated shaft approved.
|
||||
Progress Inspection | Passed | 12/8/2020 (12:30 - 2:30) | 12/8/2020 (PM) | 12/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/08/2020
Preliminary walk-through on third floor to confirm various items. Reviewed placement of grab bars in accessible bathroom, OK. Confirmed fire and smoke ratings on doors as required, approved. Confirmed Braun’s approval of fire caulking plumbing penetrations in rated walls.
|
||||
Lighting Inspection Sign | Passed | 12/09/2020 | ||
phase 3 friendship village lighting | ||||
Progress Inspection | Passed | 12/10/2020 (2:30 - 3:30) | 12/10/2020 (PM) | 12/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/10/2020
Preliminary walk-through of second floor reveals no issues of major concern. Full final inspection to be completed later.
|
||||
Progress Inspection | Passed | 12/23/2020 (2:30 - 3:30) | 12/23/2020 (PM) | 12/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/23/2020
10 day partial temporary occupancy approved for all areas except kitchen. Call for extension of temporary occupancy if required, or final inspection when ready.
|
||||
Miscellaneous/Other
Outstanding
12/23/2020
10 day partial temporary occupancy approved for all areas except kitchen. Call for extension of temporary occupancy if required or final inspection when ready.
|
||||
Building Final Inspection | Passed | 12/23/2020 (2:30 - 3:30) | 12/23/2020 (PM) | 12/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/23/2020
10 day partial temporary occupancy approved for all areas except kitchen. Call for extension of temporary occupancy as required or final when ready.
|
||||
Miscellaneous/Other
Comment Only
12/23/2020
10 day partial temporary occupancy approved for all areas except kitchen. Call for extension of temporary occupancy as required or final when ready. Temporary occupancy is for phase 1 of three phases.
|
||||
Building Final Inspection | Partial Pass | 01/19/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/19/2021
Final approval for occupancy of phase 1 approved as of January 15.
|
||||
Progress Inspection | Passed | 6/3/2021 (8:00 - 10:00) | 6/3/2021 (AM) | 06/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/03/2021
Poured foundation wall along north side of North wing approved.
|
||||
Progress Inspection | Passed | 6/10/2021 (8:00 - 10:00) | 6/10/2021 (AM) | 06/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2021
Remaining poured foundation wall approved. Pad footings as per marked plan approved.
|
||||
Progress Inspection | Passed | 6/15/2021 (2:30 - 3:30) | 6/15/2021 (PM) | 06/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/15/2021
Remaining poured wall foundation inspection for phase 2 of project, approved. Note phase 2 inspections should fall under separate permit number to be corrected on all future phase 2 inspections.
|