Permit Application Status

PRBD201903507


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201903507
Building
Finaled
G&I VIII WF PLAZA LLC
Alteration/Repair/Replace
Business
Work to bring third floor suites to spec status.
04/17/2019
05/09/2019
03/25/2020
09/27/2019

Locations

Permits

Permit Number: PRBD201903507

Building
Finaled
05/09/2019
03/25/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 5/23/2019 (8:00 - 10:00) 5/23/2019 (AM) 05/23/2019
Corrections:


Miscellaneous/Other
Carried Forward
05/23/2019
Patch fireproofing, and fill concrete ceiling penetrations from 4th floor above, east end only. Complete 1hr rated corridors on west and east side including fire-caulk penetrations. Firecaulk plumbing, electrical floor penetrations. Exit signage as discussed with emergency lighting.

Above Ceiling Inspection Partial Pass 05/23/2019
A.Patch fireproofing, floor penetrations, east end. B. Spray damn and stuff both 1 hr rated corridors at ceiling to both exit stairwells. Firecaulk plumbing, electrical penetrations on floor and rated walls. Call for reinspection when ready.
Above Ceiling Inspection Passed 6/21/2019 (8:00 - 10:00) 6/21/2019 (AM) 06/21/2019
Corrections:


Miscellaneous/Other
Comment Only
06/21/2019
Above ceiling at rated portions of corridor approved. Fireproof patching and core penetrations approved.

Fire Inspection Final Passed 9/26/2019 (2:30 - 3:30) 9/26/2019 (PM) 09/26/2019
Fire Rated Assemblies Inspection Passed 09/27/2019
Patch fireproofing on existing steel I beams before painting ceiling black.
Framing Inspection Passed 09/27/2019
Corrections:


Miscellaneous/Other
Outstanding
05/23/2019
Patch fireproofing, and fill concrete ceiling penetrations from 4th floor above, east end only. Complete 1hr rated corridors on west and east side including fire-caulk penetrations. Firecaulk plumbing, electrical floor penetrations. Exit signage as discussed with emergency lighting.

Building Final Inspection Passed 9/26/2019 (2:30 - 3:30) 9/26/2019 (PM) 09/27/2019
Final - passed.