PRBD201903566
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 07/02/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/02/2019
Viewed the mall bulkhead and framing of the buildout bulkhead for partial covering to complete framing. Access panel needed in bulkhead for electrical junction box.
|
||||
Framing Inspection | Partial Pass | 7/23/2019 (10:00 - 12:00) | 7/23/2019 (AM) | 07/23/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/23/2019
Wall framing approved.
The platform in the plenum area behind the storage needs to have extra support to help hold up the platform since it is mostly held up with non structural framing. This platform will be for access to the grease duct for maintenance cleaning.
|
||||
Framing Inspection | Passed | 8/5/2019 (8:00 - 10:00) | 8/5/2019 (AM) | 08/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2019
Approved to cover ceilings . Fire inspection to be done prior to covering.
Above ceiling approved.
|
||||
Progress Inspection | Passed | 10/02/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/02/2019
Veiwed framing of horizontal shaft at 4th floor for grease duct termination through roof, firestops for grease duct, at shaft and through floor... approved.
|
||||
Fire Inspection Final | Not Ready | 10/4/2019 (10:00 - 12:00) | 10/4/2019 (AM) | 10/04/2019 |
Building Final Inspection | Not Ready | 10/4/2019 (10:00 - 12:00) | 10/4/2019 (AM) | 10/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/04/2019
Not fully ready for final... plumbing and fire inspection final needed.
Approved to bring in small wares,stock, and train.
|
||||
Fire Inspection Final | Passed | 10/07/2019 | ||
Building Final Inspection | Passed | 10/8/2019 (8:00 - 10:00) | 10/8/2019 (AM) | 10/08/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/08/2019
Final approved, ok to open to public.
|