PRBD201903700
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Building Final Inspection | Pending | |||
| Footing Inspection | Pending | |||
| Framing Inspection | Pending | |||
| Lath Inspection | Pending | |||
| Progress Inspection | Pending | |||
| Footing Inspection | Partial Pass | 7/11/2019 (12:30 - 2:30) | 7/11/2019 (PM) | 07/11/2019 |
| Two pier footings, and two stoop footings. - location at MGM liquors west end. | ||||
| Framing Inspection | Partial Pass | 7/11/2019 (12:30 - 2:30) | 7/11/2019 (PM) | 07/11/2019 |
| Progress only. Not ready. | ||||
| Progress Inspection | Partial Pass | 08/02/2019 | ||
| Demolition of building store front, and installing structural piers, stoop foundations. A. Individual protection and definition of tenant space front entry doors during construction. B. At this time things appear clean, exterior signage for tenants, and temporary covered entrance for tenants. | ||||
| Progress Inspection | Partial Pass | 08/29/2019 | ||
| Progress Inspection | Partial Pass | 09/10/2019 | ||
| Progress: front parapet walls by steel stud. A. Need to use manufactured 90 degree clip from steel vertical studs to structure. | ||||
| Framing Inspection | Partial Pass | 9/25/2019 (12:30 - 2:30) | 9/25/2019 (PM) | 09/25/2019 |
| Progress. | ||||
| Framing Inspection | Partial Pass | 10/04/2019 | ||
| Structural iron, steel stud framing attached to structural iron, fire treated plywood sheathing and fire treated 2x4 attached to steel stud framing, gypsum board covering fire treated plywood and fire treated 2x4. 2 coat stucco with finish coat to follow. A. Need engineer approval of welding, structural iron, and steel stud fastening. | ||||
| Lath Inspection | Failed | 10/23/2019 | ||
| 1st inspection - Stucco lathe inspection with grade 75 paper. A. Need to remove corner aid on vertical surface meeting horizontal surface, and install back to back casing beams per ASTM C 926.(stucco specification standards. ) | ||||
| Lath Inspection | Partial Pass | 10/31/2019 | ||
| Progress- ASTM 96. | ||||
| Progress Inspection | Partial Pass | 12/10/2019 | ||
| Progress, on stucco, metal, for new store front exterior entry facades, for multiple existing tenants. | ||||