PRBD201905008
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 6/20/2019 (12:30 - 2:30) | 6/20/2019 (PM) | 06/20/2019 |
Corrections:
Miscellaneous/Other
Outstanding
06/20/2019
Need to view firestops at piping below the buildout.
|
||||
Miscellaneous/Other
Comment Only
06/20/2019
Framing walls and lid. Approved to cover all, pending sprinkler inspection at lid.
|
||||
Building Final Inspection | Partial Pass | 7/26/2019 (12:30 - 2:30) | 7/26/2019 (PM) | 07/26/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/26/2019
Complete cleaning and all final trades inspections.
Approved to stock small wares and dry goods ok to train staff.
Call for final inspections.
|
||||
Fire Inspection Final | Passed | 7/26/2019 (12:30 - 2:30) | 7/26/2019 (PM) | 07/29/2019 |
Building Final Inspection | Failed | 8/20/2019 (2:30 - 3:30) | 8/20/2019 (PM) | 08/20/2019 |
Corrections:
Miscellaneous/Other
Outstanding
08/20/2019
Environmental Health has corrections and needs owner present to speak with. No storage above walk in cooler as well.
This permit cannot be final until EH has approved the space. This permit can close out once EH has approved space. Not approved for opening to public at this time.
|
||||
Electrical Final Inspection | VOID | 04/09/2020 |