PRBD201905525
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 6/18/2019 (8:00 - 10:00) | 6/18/2019 (AM) | 06/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/18/2019
Framing approved
|
||||
Framing Inspection | Passed | 7/2/2019 (8:00 - 10:00) | 7/2/2019 (AM) | 07/02/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/02/2019
Above ceiling approved
|
||||
Fire Inspection Final | Passed | 7/8/2019 (2:30 - 3:30) | 7/8/2019 (PM) | 07/08/2019 |
Building Final Inspection | Passed | 7/8/2019 (2:30 - 3:30) | 7/8/2019 (PM) | 07/08/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/08/2019
Final approved.
|