PRBD201906112
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Above Ceiling Inspection | Failed | 8/16/2019 (10:00 - 12:00) | 8/16/2019 (AM) | 08/16/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
08/16/2019
1) Fireproofing at beam need.
2) Smoke seal the bulkhead
Reinspection needed, schedule when ready.
|
||||
Framing Inspection | Passed w/ Conditions | 8/16/2019 (10:00 - 12:00) | 8/16/2019 (AM) | 08/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/16/2019
Walls and ceilings approved to cover pending the inspection of the one in wall firestop at floor that feeds poke throughs.
Will check at above ceiling inspection.
|
||||
Fire Inspection Final | Passed w/ Conditions | 9/13/2019 (8:00 - 10:00) | 9/13/2019 (AM) | 09/12/2019 |
Corrections:
Fire extinguishers not installed.
Comment Only
09/12/2019
Fire extinguishers not installed. Hang per discussion.
|
||||
Building Final Inspection | Passed | 9/13/2019 (10:00 - 12:00) | 9/13/2019 (PM) | 09/14/2019 |
Approved ready to open the store | ||||
Above Ceiling Inspection | VOID | 04/09/2020 | ||
Corrections:
Miscellaneous/Other
Outstanding
08/16/2019
1) Fireproofing at beam need.
2) Smoke seal the bulkhead
Reinspection needed, schedule when ready.
|